A government agency is planning a Public Sector Solutions implementation. What are three main constraints that government agencies often have in project implementation?
A.
Workshops, Schedule and Cost
B.
Scope, Tools and Cost
C.
Scope, Resources and Cost
D.
Scope, Schedule and Cost