How is management that is external to the Scrum Team involved in the Daily Scrum?
(choose the best answer)
A.
The Product Owner represents their opinions.
B.
The Scrum Master speaks on their behalf.
C.
Managers are not required at the Daily Scrum.
D.
Management gives an update at the start of each Daily Scrum.