Question 9 - PSPO-I discussion

Report
Export

When is the Sprint Backlog created?

(choose the best answer)

A.
Prior to Sprint Planning.
Answers
A.
Prior to Sprint Planning.
B.
During refinement.
Answers
B.
During refinement.
C.
During the Sprint Retrospective.
Answers
C.
During the Sprint Retrospective.
D.
During Sprint Planning.
Answers
D.
During Sprint Planning.
Suggested answer: D

Explanation:

The Sprint Backlog is created during Sprint Planning, where the Developers select the Product Backlog items that they can deliver in the Sprint and create a plan for how to do the work.The Scrum Guide states that 'The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how).'1The Sprint Backlog is owned and managed by the Developers, who can update it throughout the Sprint as more is learned.

1: The Scrum Guide2, page 15

2:The Scrum Guide