ExamGecko
Home Home / Scrum / PSPO-I

Scrum PSPO-I Practice Test - Questions Answers, Page 17

Question list
Search
Search

What is the accountability of the Product Owner during Sprint 0?

(choose the best answer)

A.
Determine the composition of the Scrum Team to meet the release plan.
A.
Determine the composition of the Scrum Team to meet the release plan.
Answers
B.
There is no such thing as Sprint 0.
B.
There is no such thing as Sprint 0.
Answers
C.
Create the overall release plan to ensure that organizational goals are met.
C.
Create the overall release plan to ensure that organizational goals are met.
Answers
D.
Make sure enough Product Backlog items are refined to fill the first 3 Sprints.
D.
Make sure enough Product Backlog items are refined to fill the first 3 Sprints.
Answers
E.
Gathering, eliciting, and analyzing the requirements to build the Product Backlog.
E.
Gathering, eliciting, and analyzing the requirements to build the Product Backlog.
Answers
Suggested answer: B

Explanation:

Sprint 0 is a term that some organizations use to describe a phase of work before the first official Sprint, where they do some upfront planning, design, architecture, or analysis1.However, this term is not consistent with the Scrum framework, which does not prescribe any pre-Sprint activities or phases2. Scrum starts with a Product Backlog that contains at least one valuable and feasible Product Goal, and enough Product Backlog items to initiate the first Sprint[3][3].The Product Owner is accountable for maximizing the value of the product and the work of the Developers, and for managing the Product Backlog4. The Product Owner does not have any specific accountability during Sprint 0, because Sprint 0 is not a part of Scrum.

1:Sprint Zero: A Good Idea or Not?, Scrum Alliance, accessed on December 16, 2023

2:The Scrum Guide, November 2020, p. 5

[3][3]:The Scrum Guide, November 2020, p. 9

4:The Scrum Guide, November 2020, p. 6

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days?

(choose the best three answers)

A.
The Sprint Backlog may become inaccurate.
A.
The Sprint Backlog may become inaccurate.
Answers
B.
Too much work is spent updating the Scrum board before the meeting.
B.
Too much work is spent updating the Scrum board before the meeting.
Answers
C.
The Scrum Master loses the ability to update the Gantt chart properly.
C.
The Scrum Master loses the ability to update the Gantt chart properly.
Answers
D.
The Product Owner cannot accurately report progress to the stakeholders.
D.
The Product Owner cannot accurately report progress to the stakeholders.
Answers
E.
Opportunities to inspect and adapt the Sprint Backlog are lost.
E.
Opportunities to inspect and adapt the Sprint Backlog are lost.
Answers
F.
Impediments are raised and resolved more slowly.
F.
Impediments are raised and resolved more slowly.
Answers
Suggested answer: A, E, F

Explanation:

The Daily Scrum is a 15-minute event for the Developers to inspect their progress toward the Sprint Goal and adapt the Sprint Backlog as necessary1.It is a key opportunity for the Developers to plan their work for the next 24 hours and collaborate on any challenges or impediments2. If the frequency of the Daily Scrum were to be lowered to every two or three days, three key concerns would be:

The Sprint Backlog may become inaccurate. The Sprint Backlog is the plan for how the Developers will achieve the Sprint Goal, and it is updated throughout the Sprint as more is learned[3][3].The Daily Scrum is a chance for the Developers to inspect the Sprint Backlog and make adjustments based on the current situation4. If the Daily Scrum is less frequent, the Sprint Backlog may not reflect the reality of the work, and the Developers may lose track of their progress and alignment with the Sprint Goal.

Opportunities to inspect and adapt the Sprint Backlog are lost.Scrum is based on empiricism, which means that knowledge comes from experience and making decisions based on what is observed5. The Daily Scrum is an essential event for the Developers to apply empiricism to their work, by inspecting the Sprint Backlog and adapting it to optimize the value and quality of the Increment. If the Daily Scrum is less frequent, the Developers may miss opportunities to inspect and adapt their work, and may not be able to deliver a valuable, useful Increment every Sprint.

Impediments are raised and resolved more slowly. An impediment is anything that prevents the Scrum Team from delivering a product Increment. The Daily Scrum is a forum for the Developers to identify and communicate any impediments that affect their work, and to seek help from the Scrum Master or other team members. If the Daily Scrum is less frequent, the impediments may not be raised and resolved in a timely manner, and may cause delays or quality issues in the product delivery.

1:The Scrum Guide, November 2020, p. 10

2:The Scrum Guide, November 2020, p. 11

[3][3]:The Scrum Guide, November 2020, p. 10

4:Understanding and Applying the Scrum Framework, Scrum.org, accessed on December 16, 2023

5:The Scrum Guide, November 2020, p. 4

:The Scrum Guide, November 2020, p. 11

:The Scrum Guide, November 2020, p. 14

:Developing People and Teams, Scrum.org, accessed on December 16, 2023

Which approach is best for Scrum Teams in order to produce valuable Increments?

(choose the best answer)

A.
Each Developer works on the component where they feel that they can contribute.
A.
Each Developer works on the component where they feel that they can contribute.
Answers
B.
Each Scrum Team works on an independent set of components.
B.
Each Scrum Team works on an independent set of components.
Answers
C.
Each Scrum Team is accountable for developing functionality from beginning to end.
C.
Each Scrum Team is accountable for developing functionality from beginning to end.
Answers
D.
Each Scrum Member works only as an independent layer of the system.
D.
Each Scrum Member works only as an independent layer of the system.
Answers
Suggested answer: C

Explanation:

The best approach for Scrum Teams to produce valuable Increments is to be accountable for developing functionality from beginning to end, as this enables them to deliver potentially releasable products that meet the definition of "Done".The Scrum Guide states that 'The Developers are the people in the Scrum Team that are committed to creating any aspect of a usable Increment each Sprint.'1This means that the Developers are not limited by the boundaries of components, layers, or technologies, but rather they collaborate and coordinate to deliver a complete and integrated product that satisfies the Sprint Goal and the Product Owner's expectations.

1: The Scrum Guide2, page 7

2:The Scrum Guide

How much time is required after a Sprint to prepare for the next Sprint?

(choose the best answer)

A.
The break between Sprints is timeboxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
A.
The break between Sprints is timeboxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
Answers
B.
Enough time for the requirements for the next Sprint to be determined and documented.
B.
Enough time for the requirements for the next Sprint to be determined and documented.
Answers
C.
Enough time for the Developers to finish the testing from the last Sprint.
C.
Enough time for the Developers to finish the testing from the last Sprint.
Answers
D.
None. A new Sprint starts immediately following the end of the previous Sprint.
D.
None. A new Sprint starts immediately following the end of the previous Sprint.
Answers
E.
All of the above are allowed depending on the situation.
E.
All of the above are allowed depending on the situation.
Answers
Suggested answer: D

Explanation:

The Scrum Guide states that 'Sprints have consistent durations throughout a development effort.A new Sprint starts immediately after the conclusion of the previous Sprint.'1This means that there is no gap or break between Sprints, and the Scrum Team does not need to spend extra time to prepare for the next Sprint. The Scrum Team should be able to start the next Sprint Planning right after the Sprint Review and Sprint Retrospective of the previous Sprint. The Scrum Team should also ensure that the testing and documentation of the work are done within the Sprint, and not left for later.

1: The Scrum Guide2, page 9

2:The Scrum Guide

During the Sprint Retrospective a Scrum Team has identified several high priority process improvements. Which of the following statements is most accurate?

(choose the best answer)

A.
The Scrum Team may add the items to the Sprint Backlog for the next Sprint.
A.
The Scrum Team may add the items to the Sprint Backlog for the next Sprint.
Answers
B.
The Scrum Team should decline to add a process improvement to the Sprint Backlog when things are running smoothly.
B.
The Scrum Team should decline to add a process improvement to the Sprint Backlog when things are running smoothly.
Answers
C.
The Scrum Team should choose at least one high priority process improvement to place in the Product Backlog.
C.
The Scrum Team should choose at least one high priority process improvement to place in the Product Backlog.
Answers
D.
The Scrum Master selects the most important process improvement and places it in the Sprint Backlog
D.
The Scrum Master selects the most important process improvement and places it in the Sprint Backlog
Answers
Suggested answer: A

Explanation:

The Scrum Guide states that 'By the end of the Sprint Retrospective, the Scrum Team should have identified improvements that it will implement in the next Sprint.Implementing these improvements in the next Sprint is the adaptation to the inspection of the Scrum Team itself.'1This means that the Scrum Team may add the high priority process improvements to the Sprint Backlog for the next Sprint, as part of their plan to deliver the Increment and achieve the Sprint Goal.The Sprint Backlog is owned and managed by the Developers, who can update it throughout the Sprint as more is learned.1

1: The Scrum Guide2, page 16

2:The Scrum Guide

What does it mean to say that an event has a timebox?

(choose the best answer)

A.
The event can take no more than a maximum amount of time.
A.
The event can take no more than a maximum amount of time.
Answers
B.
The event must take at least a minimum amount of time.
B.
The event must take at least a minimum amount of time.
Answers
C.
The event must happen by a given time.
C.
The event must happen by a given time.
Answers
D.
The event must happen at a set time.
D.
The event must happen at a set time.
Answers
Suggested answer: A

Explanation:

To say that an event has a timebox means that the event has a fixed duration that cannot be exceeded. The Scrum Guide states that 'All events are time-boxed events, such that every event has a maximum duration. Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened.The remaining events may end whenever the purpose of the event is achieved, ensuring an appropriate amount of time is spent without allowing waste in the process.'1This means that the timebox sets an upper limit for the event, but the event can end sooner if the goal is met.

1: The Scrum Guide2, page 10

2:The Scrum Guide

What is a Product Owner typically responsible for during a Sprint?

(choose the best two answers)

A.
Attending every Daily Scrum to answer questions about the Sprint Backlog items.
A.
Attending every Daily Scrum to answer questions about the Sprint Backlog items.
Answers
B.
Creating financial reporting upon the spent hours reported by the Developers.
B.
Creating financial reporting upon the spent hours reported by the Developers.
Answers
C.
Nothing.
C.
Nothing.
Answers
D.
Updating the work plan for the Developers on a daily basis.
D.
Updating the work plan for the Developers on a daily basis.
Answers
E.
Collaborating with stakeholders, users, and customers.
E.
Collaborating with stakeholders, users, and customers.
Answers
F.
Working with the Scrum Team on Product Backlog refinement.
F.
Working with the Scrum Team on Product Backlog refinement.
Answers
Suggested answer: E, F

Explanation:

The Product Owner is typically responsible for collaborating with stakeholders, users, and customers to understand their needs and expectations, and to validate the value of the product.The Product Owner is also responsible for working with the Scrum Team on Product Backlog refinement, which is the act of adding detail, estimates, and order to Product Backlog items.1These two responsibilities help the Product Owner to maximize the value of the product and the work of the Developers.

1: The Scrum Guide2, page 18

2:The Scrum Guide

Which of the following is an example of an Increment?

(choose the best answer)

A.
A plan for the overall product release.
A.
A plan for the overall product release.
Answers
B.
A mock-up of the product marketing materials.
B.
A mock-up of the product marketing materials.
Answers
C.
A design for the product.
C.
A design for the product.
Answers
D.
A product roll-out plan.
D.
A product roll-out plan.
Answers
E.
A valuable, useful set of product features.
E.
A valuable, useful set of product features.
Answers
F.
All of the above.
F.
All of the above.
Answers
Suggested answer: E

Explanation:

An Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints.1An Increment is a concrete, tangible, and usable outcome of the work done by the Developers in a Sprint. It is not a plan, a mock-up, a design, or a roll-out plan, as these are not valuable or useful products in themselves.An Increment must meet the definition of "Done", which means it must adhere to the quality standards agreed upon by the Scrum Team and the stakeholders.1An Increment must also be potentially releasable, which means it must be in a state that it could be delivered to the customer or user if the Product Owner decides so.1

1: The Scrum Guide2, page 14

2:The Scrum Guide

A product's success is measured by:

(choose the best three answers)

A.
The impact on cost.
A.
The impact on cost.
Answers
B.
The impact on my performance rating.
B.
The impact on my performance rating.
Answers
C.
The impact on revenue.
C.
The impact on revenue.
Answers
D.
The impact on my boss's mood.
D.
The impact on my boss's mood.
Answers
E.
The delivery of upfront defined scope compared to the upfront planned time.
E.
The delivery of upfront defined scope compared to the upfront planned time.
Answers
F.
The impact on customer satisfaction.
F.
The impact on customer satisfaction.
Answers
Suggested answer: A, C, F

Explanation:

A product's success is measured by the value it delivers to the customers and the organization. The impact on cost, revenue, and customer satisfaction are three important indicators of value.The Scrum Guide states that 'The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team.'1The Product Owner should consider the cost of developing and maintaining the product, the revenue generated by the product, and the satisfaction of the customers and users who use the product. These factors help the Product Owner to prioritize the Product Backlog, define the Product Goal, and collaborate with the stakeholders.

1: The Scrum Guide2, page 6

2:The Scrum Guide

What is the typical size for a Scrum Team?

(choose the best answer)

A.
At least 7.
A.
At least 7.
Answers
B.
9.
B.
9.
Answers
C.
10 or fewer.
C.
10 or fewer.
Answers
D.
7 plus or minus 3.
D.
7 plus or minus 3.
Answers
Suggested answer: C

Explanation:

The typical size for a Scrum Team is 10 or fewer people, including the Product Owner, the Scrum Master, and the Developers. The Scrum Guide states that 'The Scrum Team is small enough to remain nimble and large enough to complete significant work within a Sprint. Fewer than three people decrease interaction and results in smaller productivity gains. Having more than ten people requires too much coordination.Large teams generate too much complexity for an empirical process to be useful.'1This means that the optimal Scrum Team size is between 3 and 10 people, depending on the context and the nature of the work.

1: The Scrum Guide2, page 6

2:The Scrum Guide

Total 171 questions
Go to page: of 18