Question 30 - PSPO-I discussion
A Scrum Master is working with a Scrum Team that has Developers in different physical locations. The Developers meet in a variety of meeting rooms and have much to do logistically
(for example: reserve meeting rooms and set up conference calls) before the Daily Scrum.
What action should the Scrum Master take?
(choose the best answer)
A.
Allow the Developers to self-manage and determine for themselves what to do.
B.
Ask the Developers to alternate who is responsible for meeting setup.
C.
Set up the meeting and tell the Scrum Team that is how it will be done.
D.
Inform management and ask them to solve it.