Question 82 - PSPO-I discussion

Report
Export

Scrum requires that the Product Owner must use which of the following items?

(choose all that apply)

A.
Burndown chart.
Answers
A.
Burndown chart.
B.
Feature burn-up.
Answers
B.
Feature burn-up.
C.
Critical Path Analysis.
Answers
C.
Critical Path Analysis.
D.
Project Gantt chart.
Answers
D.
Project Gantt chart.
E.
None of the above.
Answers
E.
None of the above.
Suggested answer: E

Explanation:

Scrum does not require that the Product Owner must use any of the following items:

Burndown chart: A burndown chart is a graphical representation of work left to do versus time. It can be used to track progress and forecast completion dates of projects or Sprints. However, it is not mandatory or prescribed in Scrum. It is one of the possible techniques that a Product Owner may use to monitor and communicate product development.

Feature burn-up: A feature burn-up chart is a graphical representation of features completed versus time. It can be used to track progress and forecast scope changes of projects or Sprints. However, it is not mandatory or prescribed in Scrum. It is one of the possible techniques that a Product Owner may use to monitor and communicate product development.

Critical Path Analysis: Critical Path Analysis is a project management technique that identifies the sequence of tasks that must be completed on time for a project or Sprint to finish on schedule. It can be used to plan, monitor, and control complex projects or Sprints. However, it is not mandatory or prescribed in Scrum. It is one of the possible techniques that a Product Owner may use to manage product development.

Project Gantt chart: A project Gantt chart is a graphical representation of tasks, dependencies, durations, and milestones of a project or Sprint. It can be used to plan, monitor, and control complex projects or Sprints. However, it is not mandatory or prescribed in Scrum. It is one of the possible techniques that a Product Owner may use to manage product development.

Therefore, the correct answer is none of the above.

[Scrum Guide], page 6, section "Product Owner"

[Scrum Guide], page 11, section "Product Backlog"

[Professional Scrum Product Owner Training], page 8, section "Release Management"