True or False: Product Owners must specify complete acceptance criteria for a Product

Backlog item before the Developers can select the item in Sprint Planning.

A.
True
Answers
A.
True
B.
False
Answers
B.
False
Suggested answer: B

Explanation:

Very Short Explanation: According to Scrum.org, the Product Owner is not required to create clear and unambiguous acceptance criteria for each item in the product's backlog before it can be selected in Sprint Planning1. Acceptance Criteria is optional and is not prescribed by Scrum12. It can be valuable, but it's not a must12. The Developers can inspect and adapt the Sprint Backlog in any way they see fit, in order to help meet the Sprint Goal2.