What is the Product Owner responsible for during the Sprint Retrospective?

(choose the best answer)

A.
Summarizing and reporting the discussions to the stakeholders that they represent in the Scrum Team.
Answers
A.
Summarizing and reporting the discussions to the stakeholders that they represent in the Scrum Team.
B.
The Product Owner should not take part in Sprint Retrospective.
Answers
B.
The Product Owner should not take part in Sprint Retrospective.
C.
Participating as a Scrum Team member.
Answers
C.
Participating as a Scrum Team member.
D.
Capturing requirements for the Product Backlog.
Answers
D.
Capturing requirements for the Product Backlog.
Suggested answer: C