Question 105 - PSPO-I discussion

Report
Export

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

(choose the best answer)

A.
Methods of communication.
Answers
A.
Methods of communication.
B.
The way the Scrum Team does Sprint Planning.
Answers
B.
The way the Scrum Team does Sprint Planning.
C.
Skills needed to improve the Developers ability to deliver.
Answers
C.
Skills needed to improve the Developers ability to deliver.
D.
The Definition of Done.
Answers
D.
The Definition of Done.
E.
All of the above.
Answers
E.
All of the above.
Suggested answer: E

Explanation:

During the Sprint Retrospective, the Scrum Team discusses how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done123. This includes methods of communication, the way the Scrum Team does Sprint Planning, skills needed to improve the Developers' ability to deliver, and the Definition of Done123.