Question 108 - PSPO-I discussion

Report
Export

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done?

(choose the best answer)

A.
Without a new vocabulary as a reminder of the change, very little change may actually happen.
Answers
A.
Without a new vocabulary as a reminder of the change, very little change may actually happen.
B.
The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.
Answers
B.
The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.
C.
Management may feel less anxious.
Answers
C.
Management may feel less anxious.
D.
All answers apply.
Answers
D.
All answers apply.
Suggested answer: D