Question 129 - PSPO-I discussion

Report
Export

True or False: The Product Owner makes sure the Developers select enough from the Product

Backlog for a Sprint to satisfy the stakeholders.

A.
True
Answers
A.
True
B.
False
Answers
B.
False
Suggested answer: B

Explanation:

The Product Owner does not make sure the Developers select enough from the Product Backlog for a Sprint.The Product Owner is responsible for maximizing the value of the product and the work of the Developers, but the Developers are self-managing and decide how much work they can do in a Sprint1.The Product Owner and the Developers collaborate on the scope of the Sprint during Sprint Planning, but the final decision is up to the Developers2. The Product Owner should not interfere with the Developers' work during the Sprint, but should provide feedback and guidance on the product value[3][3].

1:The Scrum Guide, November 2020, p. 6

2:The Scrum Guide, November 2020, p. 10

[3][3]:Professional Scrum Product Owner I Certification, Scrum.org, accessed on December 16, 2023

asked 23/09/2024
Tyler Sent
26 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first