Question 133 - PSPO-I discussion
When must the Product Owner participate in the Daily Scrum?
(choose the best answer)
A.
When the Scrum Master asks the Product Owner to attend.
B.
When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer.
C.
When there are impediments to discuss.
D.
When the Product Owner needs to represent the stakeholders' point of view to the Developers.