Question 168 - PSPO-I discussion

Report
Export

Which of the following is an example of an Increment?

(choose the best answer)

A.
A plan for the overall product release.
Answers
A.
A plan for the overall product release.
B.
A mock-up of the product marketing materials.
Answers
B.
A mock-up of the product marketing materials.
C.
A design for the product.
Answers
C.
A design for the product.
D.
A product roll-out plan.
Answers
D.
A product roll-out plan.
E.
A valuable, useful set of product features.
Answers
E.
A valuable, useful set of product features.
F.
All of the above.
Answers
F.
All of the above.
Suggested answer: E

Explanation:

An Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints.1An Increment is a concrete, tangible, and usable outcome of the work done by the Developers in a Sprint. It is not a plan, a mock-up, a design, or a roll-out plan, as these are not valuable or useful products in themselves.An Increment must meet the definition of "Done", which means it must adhere to the quality standards agreed upon by the Scrum Team and the stakeholders.1An Increment must also be potentially releasable, which means it must be in a state that it could be delivered to the customer or user if the Product Owner decides so.1

1: The Scrum Guide2, page 14

2:The Scrum Guide