Question 171 - PSPO-I discussion

Report
Export

The Product Owner is the person who will be held accountable if a product does not achieve its goals or deliver value. Does this mean that the Product Owner has final say over the Definition of Done?

(choose the best answer)

A.
Yes, the Product Owner decides the Definition of Done. The Developers may be consulted.
Answers
A.
Yes, the Product Owner decides the Definition of Done. The Developers may be consulted.
B.
No, the Scrum Team decides the Definition of Done, if it is not a standard of the organization. The Product Owner is just one member of the Scrum Team.
Answers
B.
No, the Scrum Team decides the Definition of Done, if it is not a standard of the organization. The Product Owner is just one member of the Scrum Team.
Suggested answer: B

Explanation:

The Definition of Done is a shared understanding of what it means for work to be complete, and to ensure transparency. The Scrum Guide states that 'The Developers are required to conform to the Definition of Done, as defined by the Scrum Team.If there are multiple Scrum Teams working together on a product, they must mutually define and comply with the same Definition of Done.'1This means that the Product Owner does not have the final say over the Definition of Done, but rather collaborates with the Developers and the Scrum Master to agree on the quality standards and expectations for the product.

1: The Scrum Guide2, page 14

2:The Scrum Guide