TotalComms is a telecommunications company formed from the merging of other 2 telecommunication companies. The business operating model has been unified, the TOGAF 9 Architecture Board approved the outline Implementation and Migration Plan the detailed migration planning must know be approved. Your help is needed to work on the migration planning with all the key stakeholders to achieve an agreement.
Refer to the scenario above You are the Lead Architect asked to describe accordingly to TOGAF 9 the best way to address the following activities: The way the migration planning is conducted.
What is going to be implemented.
The stakeholders involved in the implementation.
The definition of the deliverables to use Choose one of the following answers