Please read this scenario prior to answering the question
You are serving as the Lead Architect for the Enterprise Architecture team at a multinational company. The company has grown rapidly by acquisition and has inherited numerous supply chain processes and related IT systems. Several supply chain processes have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant processes and systems. The company will move to a "Just-in-time" supply chain management so as to keep inventory costs low.
The TOGAF standard is followed for internal Enterprise Architecture activities. This project is using an iterative approach for executing the Architecture Development Method (ADM).
At present, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created.
The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing supply chain management processes or systems.
The architecture development project has completed Phase A and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures. Key stakeholder concerns that should be addressed by these architectures include: