What is an objective of the ADM Implementation Governance Phase?

A.
To provide continual monitoring of the governance framework
Answers
A.
To provide continual monitoring of the governance framework
B.
To ensure conformance for the target architecture
Answers
B.
To ensure conformance for the target architecture
C.
To finalize the Implementation and Migration Plan
Answers
C.
To finalize the Implementation and Migration Plan
D.
To establish the resources for architecture governance
Answers
D.
To establish the resources for architecture governance
Suggested answer: B

Explanation:

The objective of the ADM Implementation Governance Phase is to provide an architectural oversight of the implementation and to ensure conformance for the target architecture. This phase involves establishing procedures and processes to monitor and control the implementation projects and to verify that they comply with the defined architecture.

Reference: The TOGAF Standard | The Open Group Website, Section 3.2.7 Phase G: Implementation Governance.