Which statement about Requirements Management is most correct?

A.
The purpose of Requirements Management is to process change requests
Answers
A.
The purpose of Requirements Management is to process change requests
B.
Stakeholder requirements are captured once in Phase A and managed throughout the ADM cycle
Answers
B.
Stakeholder requirements are captured once in Phase A and managed throughout the ADM cycle
C.
Requirements Management is a step of all ADM Phases
Answers
C.
Requirements Management is a step of all ADM Phases
D.
Requirements Management and stakeholder engagement are placed at the center of architecture development
Answers
D.
Requirements Management and stakeholder engagement are placed at the center of architecture development
Suggested answer: D

Explanation:

This statement about Requirements Management is most correct because it reflects the central role of Requirements Management and stakeholder engagement in the ADM cycle. Requirements Management is not a step of all ADM Phases, but rather an ongoing process that ensures that all relevant requirements are elicited, analyzed, prioritized, and addressed throughout the architecture development and transition. Stakeholder engagement is also a continuous activity that involves identifying, communicating, and managing stakeholder expectations and concerns.

Reference: The TOGAF Standard | The Open Group Website, Section 3.1 Introduction to the ADM.