Refer to the exhibit.

An administrator has been informed that a new workload will be deployed in six months with these characteristics.

• CPU: 210 GHz

• Memory: 600 GiB

• Storage:11.72 TiB

Upon receiving the new project notification, the administrator creates a scenario to determine whether or not the Nutanix cluster has enough space capacity to properly handle the new workload.

Why is the Overall Cluster runway showing that cluster resources are not exhausted (red color)?

A.
Target analysis timeframe starts after additional resources are added.
Answers
A.
Target analysis timeframe starts after additional resources are added.
B.
There are enough available resources to support the new workload.
Answers
B.
There are enough available resources to support the new workload.
C.
Additional resources will be added before the new workload is added
Answers
C.
Additional resources will be added before the new workload is added
D.
Target analysis timeframe ends before the new workload is added.
Answers
D.
Target analysis timeframe ends before the new workload is added.
Suggested answer: D

Explanation:

https://support-portal.nutanix.com/page/documents/details?targetId=Prism-CentralGuide-Prismv5_19:mul-resource-planning-runway-view-pc-r.html

asked 23/09/2024
Rambo Jhon
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first