An administrator has been informed of a new project, which requires expanding the capacity of the project team's Volume Group without disrupting availability or affecting performance Which steps should the administrator take to achieve this?

A.
Clone the existing Volume Group to a larger instance and switch to the new Volume Group
Answers
A.
Clone the existing Volume Group to a larger instance and switch to the new Volume Group
B.
Add new dishes to the Volume Group and wait for the Volume Group to auto-resize
Answers
B.
Add new dishes to the Volume Group and wait for the Volume Group to auto-resize
C.
Create a new larger Volume Group and migrate the files
Answers
C.
Create a new larger Volume Group and migrate the files
D.
Add new data to the Volume Group and expand the Volume Group online
Answers
D.
Add new data to the Volume Group and expand the Volume Group online
Suggested answer: B