Question 5 - NCSC-Level-1 discussion
A consultant needs to verify the make and model of the systems that will be imaged with Foundation. The consultant does not have the Bill of Materials (BOM) available to review.
When should the consultant verify the make and model to prepare for the cluster deployment?
A.
During the Foundation Process
B.
While conducting the Tech Review Call
C.
Upon arriving on-site
D.
When reviewing the Statement of Work (SOW)
Your answer: