ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 1 - AZ-120 discussion

Report
Export

You are evaluating which migration method Litware can implement based on the current environment and the business goals. Which migration method will cause the least amount of downtime?

A.
Migrate SAP ECC to SAP Business Suite in HANA, and then migrate SAP to Azure.
Answers
A.
Migrate SAP ECC to SAP Business Suite in HANA, and then migrate SAP to Azure.
B.
Use Near-Zero Downtime (NZDT) to migrate to SAP HANA and Azure during the same maintenance window.
Answers
B.
Use Near-Zero Downtime (NZDT) to migrate to SAP HANA and Azure during the same maintenance window.
C.
Use the Database Migration Option (DMO) to migrate to SAP HANA and Azure during the same maintenance window.
Answers
C.
Use the Database Migration Option (DMO) to migrate to SAP HANA and Azure during the same maintenance window.
D.
Migrate SAP to Azure, and then migrate SAP ECC to SAP Business Suite on HANA.
Answers
D.
Migrate SAP to Azure, and then migrate SAP ECC to SAP Business Suite on HANA.
Suggested answer: C

Explanation:

The SAP Database Migration Option (DMO) with System Move option of SUM, used as part of the migration allows customer the options to perform the migration in a single step, from source system on-premises, or to the target system residing in Microsoft Azure, minimizing overall downtime.

Reference:

https://blogs.sap.com/2017/10/05/your-sap-on-azure-part-2-dmo-with-system-move/

asked 02/10/2024
Alper Atar
32 questions
NextNext
User
Your answer:
0 comments
Sorted by

Leave a comment first