Currently, the Done column of the Finance board shows all issues ever completed, regardless of age. Now, the team wants to do a periodic clean-up of the Done column.
* They want to do the clean-up whenever it is needed on an ad-hoc basis.
* They want to be able to report on all the issues that were removed during each clean-up.
Which solution meets their need?
Analyze the component configuration of a project as shown.
Dave creates an issue and wants to use the auto-assignment feature of Jir
a. Which statement is definitely correct?
You need a field that:
* allows different options in different projects
* allows options to be disabled where necessary
* allows only a single value
* allows a default value to be configured
Which field meets these requirements?
Your company recently created an internal IT project to track hardware requests. View the project configuration below: Project: Hardware request Project lead: Allen Frank Default Assignee: Project lead
To test the triaging process you create the first issue in the project and select the Macbook 13' component. You don t update the assignee field and leave it to the default value of Automatic.
Based on the current configuration, which value will the assignee field show after creating the test issue?
The team wants to flag issues using a category. Their requirements are:
* more than one category value can be selected on an issue
* new category values can be added by any user
* category values can be selected via a dropdown menu
* category values can be re-used across all projects
Which field meets their requirements?
Which statement is definitely true about priorities in Jira?
Jon notices that an issue was created incorrectly in project
All stories in your project are linked to epics within the same project. Using a bulk operation, you moved some stories to another project. What happens to the epics?
A Scrum project has the following five configured versions:
How many of them will be available in the versions panel of the project backlog?
You are Tasked with restoring archived sub-tasks in a project.
The project to which the sub-tasks belong has since been archived, as well.
Which is the toned course of action?
Question