SAP C_S43_2023 Practice Test - Questions Answers, Page 8
List of questions
Related questions
Which are the prerequisites for Inspection Checklist Processing? Note: There are 2 correct answers to this question
QM inspection plan with assigned inspection characteristics
Inspection point type assigned to the task list header
Master inspection characteristics assigned to PM task list operations
Classification data assigned to a technical object
What do you have to consider when implementing Ul technologies in SAP S/4HANA Asset Management? Note: There are 2 correct answers to this question
Web Dynpro apps can be used in the SAP Fiori Launchpad.
SAP Fiori Launchpad supports only SAPUIS apps.
SAP GUI for HTML can be used in the SAP Fiori Launchpad.
The cloud version can also use SAP GUI for Windows.
What are valid item categories for a BOM used in Asset Management? Note: There are 3 correct answers to this question.
D (Document item)
I (PM Structure element)
F (Functional location)
L (Stock item)
E (Equipment)
You want to assign components to a General Maintenance Task List. What are prerequisites for assigning material components to a task list operation? Note: There are 2 correct answers to this question
Assign the header material of a material BOM as assembly to a task list operation.
Assign the BOM usage for free assignment of material in Customizing
Assign the header material of a material ROM to the assembly field of the task list header
Assign a piece of equipment with allocated material BOM to a task list operation.
Which views can you assign to an equipment category via a view profile? Note: There are 2 correct answers to this question?
Warranty
Configuration
Serial data
Manufacturer data
You cancel the technical completion of a work order. What are the effects? Note: There are 2 correct answers to this question?
Open reservations are recompiled.
Open purchase requisitions are recompiled
Referenced notifications are put in Process again.
Open purchase orders are recompiled.
You want to have several plan dates calculated in a maintenance plan.Which scheduling parameter do you use?
Scheduling indicator
Scheduling period
End Date for Scheduling
Call horizon
What do you have to consider when setting up the refurbishment process?
Assign valuation type C to the order type.
Assign a view profile for refurbishment to the order type.
Assign a stock determination rule to the PM order type
Mark the order type for refurbishment in customizing.
The maintenance technician wants to document work steps for a technical object in a notification. What are the best options to be used in regard to code-based reporting? Note: There are 2 correct answers to this question?
A text in the subject long text screen
An entry in the object list
A task in the notification item
An activity in the notification header
Which of the below objects can you assign in a notification item? Note: There are 2 correct answers to this question
Only one object part
One or more causes of damage.
Only one cause of damage
One or more object parts
Question