ExamGecko
Home Home / SAP / C_TS422_2023

SAP C_TS422_2023 Practice Test - Questions Answers, Page 7

Question list
Search
Search

List of questions

Search

Related questions











What does a line hierarchy in repetitive manufacturing represent?

A.

A production line with more than one work center

A.

A production line with more than one work center

Answers
B.

A production line with an alternative sequence in the routing

B.

A production line with an alternative sequence in the routing

Answers
C.

A production line with a parallel sequence in the routing

C.

A production line with a parallel sequence in the routing

Answers
D.

A production line with prioritized alternative work centers

D.

A production line with prioritized alternative work centers

Answers
Suggested answer: A

How can you set up the supply source for the Kanban process in SAP S/4HANA Cloud Private Edition? Note: There are 3 correct answers to this question.

A.

Use run schedule quantities for inhouse production.

A.

Use run schedule quantities for inhouse production.

Answers
B.

Use stock transfer reservations for stock transfer.

B.

Use stock transfer reservations for stock transfer.

Answers
C.

Use purchase orders for external procurement.

C.

Use purchase orders for external procurement.

Answers
D.

Use quotations for internal external procurement.

D.

Use quotations for internal external procurement.

Answers
E.

Use purchasing costs for automated source prioritization.

E.

Use purchasing costs for automated source prioritization.

Answers
Suggested answer: A, B, C

Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

A.

Post the goods receipt for the finished product.

A.

Post the goods receipt for the finished product.

Answers
B.

Reduce run schedule quantities.

B.

Reduce run schedule quantities.

Answers
C.

Post production costs to the planned order.

C.

Post production costs to the planned order.

Answers
D.

Update statistics for the Business Information Warehouse.

D.

Update statistics for the Business Information Warehouse.

Answers
E.

Create associated capacity requirements.

E.

Create associated capacity requirements.

Answers
Suggested answer: B, C, E

What information do you have to maintain to define the relationship between supply source dem source in the Kanban process? Note: There are 2 correct answers to this question.

A.

Routing

A.

Routing

Answers
B.

Work Center

B.

Work Center

Answers
C.

Replenishment strategy

C.

Replenishment strategy

Answers
D.

Production supply area

D.

Production supply area

Answers
Suggested answer: C, D

You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched.

How does the insertion take place?

A.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

A.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

Answers
B.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

B.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

Answers
C.

The new operation is inserted at the desired time; the previously dispatched operation is moved forward.

C.

The new operation is inserted at the desired time; the previously dispatched operation is moved forward.

Answers
D.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward.

D.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward.

Answers
Suggested answer: D

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?

Note: There are 2 correct answers to this question.

A.

Order (pool) chart

A.

Order (pool) chart

Answers
B.

Capacity requirements chart

B.

Capacity requirements chart

Answers
C.

Orders (dispatched) chart

C.

Orders (dispatched) chart

Answers
D.

Work center capacities chart

D.

Work center capacities chart

Answers
Suggested answer: B, D

What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.

A.

You can reschedule the operation using lead time scheduling.

A.

You can reschedule the operation using lead time scheduling.

Answers
B.

You can reschedule the operation using infinite scheduling in a planning table.

B.

You can reschedule the operation using infinite scheduling in a planning table.

Answers
C.

You can reschedule the operation using finite scheduling in a planning table.

C.

You can reschedule the operation using finite scheduling in a planning table.

Answers
D.

You can reschedule the operation in the Manage Work Center Capacity app.

D.

You can reschedule the operation in the Manage Work Center Capacity app.

Answers
Suggested answer: C, D

You want to trigger inhouse production of a semifinished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semifinished material?

A.

Assembly processing with production orders (82)

A.

Assembly processing with production orders (82)

Answers
B.

Planning with final assembly (40)

B.

Planning with final assembly (40)

Answers
C.

Production by lot size (30)

C.

Production by lot size (30)

Answers
D.

Planning at assembly level (70)

D.

Planning at assembly level (70)

Answers
Suggested answer: D

You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

A.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Individual/Collective indicator.

A.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Individual/Collective indicator.

Answers
B.

Choose planning strategy 20 (MaketoOrder) select the corresponding Mixed MRP indicator.

B.

Choose planning strategy 20 (MaketoOrder) select the corresponding Mixed MRP indicator.

Answers
C.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Mixed MRP indicator.

C.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Mixed MRP indicator.

Answers
D.

Choose planning strategy 20 (MaketoOrder) select the corresponding Individual/Collective indicator.

D.

Choose planning strategy 20 (MaketoOrder) select the corresponding Individual/Collective indicator.

Answers
Suggested answer: D

Your project team decides to use a maketoorder planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.

A.

Net requirements calculation is carried out for every sales order individually.

A.

Net requirements calculation is carried out for every sales order individually.

Answers
B.

Production orders are created with sales order reference.

B.

Production orders are created with sales order reference.

Answers
C.

Storage location MRP areas are required for salesorderspecific stock.

C.

Storage location MRP areas are required for salesorderspecific stock.

Answers
D.

Both the reduction of maketoorder stock requirements occur on delivery.

D.

Both the reduction of maketoorder stock requirements occur on delivery.

Answers
E.

Sales orders have to be ATPconfirmed (availabletopromise) to be saved.

E.

Sales orders have to be ATPconfirmed (availabletopromise) to be saved.

Answers
Suggested answer: A, B, E
Total 79 questions
Go to page: of 8