How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.

A.

By material type

A.

By material type

Answers
B.

By plant

B.

By plant

Answers
C.

By period

C.

By period

Answers
D.

By material status

D.

By material status

Answers
Suggested answer: B, C

Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.

A.

Opening period

A.

Opening period

Answers
B.

Total replenishment lead time

B.

Total replenishment lead time

Answers
C.

Float after production

C.

Float after production

Answers
D.

Setup time

D.

Setup time

Answers
Suggested answer: C, D

How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.

A.

Digital signature

A.

Digital signature

Answers
B.

Approved resources

B.

Approved resources

Answers
C.

Recipe approval

C.

Recipe approval

Answers
D.

GMPcompliant flag

D.

GMPcompliant flag

Answers
E.

Batch record

E.

Batch record

Answers
Suggested answer: A, C, E

Your quality department detects a deviation in a raw material batch. Unfortunately this batch has already been used in production. How can you identify all affected finished goods stocks?

Note: There are 2 correct answers to this question.

A.

Use batch determination.

A.

Use batch determination.

Answers
B.

Use the Batch Information Cockpit.

B.

Use the Batch Information Cockpit.

Answers
C.

Use the batch whereused list.

C.

Use the batch whereused list.

Answers
D.

Use batch derivation.

D.

Use batch derivation.

Answers
Suggested answer: B, C

Your project uses process orders for the production of liquid chemicals.

What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.

A.

Resource hierarchy

A.

Resource hierarchy

Answers
B.

Resource selection

B.

Resource selection

Answers
C.

Resource matrix

C.

Resource matrix

Answers
D.

Resource network

D.

Resource network

Answers
Suggested answer: B, D

Your company manufactures materials whose characteristics differ for each manufacturing process.

Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track use this information in all areas of logistics?

A.

Process order management

A.

Process order management

Answers
B.

Engineering change management

B.

Engineering change management

Answers
C.

Quality management

C.

Quality management

Answers
D.

Batch management

D.

Batch management

Answers
Suggested answer: D

What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

Answers
B.

The work center has several individual capacities.

B.

The work center has several individual capacities.

Answers
C.

Alternative work centers are fully occupied.

C.

Alternative work centers are fully occupied.

Answers
D.

The Change Planning Direction indicator is set in the strategy profile.

D.

The Change Planning Direction indicator is set in the strategy profile.

Answers
Suggested answer: A, B

What is a work center hierarchy?

A.

A group of alternative work centers for production structured in hierarchy levels by priorities

A.

A group of alternative work centers for production structured in hierarchy levels by priorities

Answers
B.

A group of alternative work centers providing a cumulative available capacity for production

B.

A group of alternative work centers providing a cumulative available capacity for production

Answers
C.

A group of work centers in a production line being used in sequence for production

C.

A group of work centers in a production line being used in sequence for production

Answers
D.

A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel

D.

A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel

Answers
Suggested answer: B

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.

A.

Queue time

A.

Queue time

Answers
B.

Teardown time

B.

Teardown time

Answers
C.

Move time

C.

Move time

Answers
D.

Setup time

D.

Setup time

Answers
Suggested answer: A, C
Total 79 questions