How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.
By material type
By plant
By period
By material status
Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.
Opening period
Total replenishment lead time
Float after production
Setup time
How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.
Digital signature
Approved resources
Recipe approval
GMPcompliant flag
Batch record
Your quality department detects a deviation in a raw material batch. Unfortunately this batch has already been used in production. How can you identify all affected finished goods stocks?
Note: There are 2 correct answers to this question.
Use batch determination.
Use the Batch Information Cockpit.
Use the batch whereused list.
Use batch derivation.
Your project uses process orders for the production of liquid chemicals.
What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.
Resource hierarchy
Resource selection
Resource matrix
Resource network
Your company manufactures materials whose characteristics differ for each manufacturing process.
Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track use this information in all areas of logistics?
Process order management
Engineering change management
Quality management
Batch management
What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.
The Finite Scheduling indicator is NOT set in the strategy profile.
The work center has several individual capacities.
Alternative work centers are fully occupied.
The Change Planning Direction indicator is set in the strategy profile.
What is a work center hierarchy?
A group of alternative work centers for production structured in hierarchy levels by priorities
A group of alternative work centers providing a cumulative available capacity for production
A group of work centers in a production line being used in sequence for production
A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.
Queue time
Teardown time
Move time
Setup time