ServiceNow CIS-SPM Practice Test - Questions Answers, Page 2

List of questions
Question 11

On the demand form, what does the Discount Rate impact?
According to the ServiceNow documentation1, the discount rate on the demand form impacts the net present value (NPV) of the demand. The NPV is the difference between the present value of the benefits and the present value of the costs of the demand. The discount rate is the rate used to discount future cash flows to their present value. A higher discount rate means that future cash flows are worth less in the present, and vice versa. The other options are incorrect because:
A) ROI: The ROI (return on investment) is the ratio of the net value to the estimated cost of the demand.The discount rate does not affect the ROI, as both the net value and the estimated cost are based on the present value of the cash flows2.
C) Financial Benefit: The financial benefit is the sum of the present value of the benefits of the demand.The discount rate does not affect the financial benefit directly, but only indirectly through the NPV calculation3.
D) Internal Rate of Return %: The internal rate of return % (IRR) is the discount rate that makes the NPV of the demand equal to zero.The discount rate does not affect the IRR, but rather the IRR is derived from the NPV equation4.
1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/reference/r_DemandTable.html2: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_DemandRate.html3: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_FinancialBenefit.html4: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_InternalRateOfReturn.html
Question 12

In which table can you find cost information for a specific fiscal period?
Question 13

Use this table to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace.
Question 14

The Business Unit field on a Project or Demand form displays values from a specific table. What type of field is this?
Question 15

What role can configure the default columns in the project planning console?
Choose 2 answers
Question 16

If a project manager is responsible for approving time sheets or submitting time cards on behalf of team members, they should be given what role?
Question 17

How many WBS levels can be shown on the planning console?
Question 18

Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
Question 19

Where is planned cost calculated from when requesting resources from a group and when resource role is specified?
Question 20

If a sub-project and parent project have different project currencies, this property should be set to true for cost roll-ups.
Question