Question 61

Report Export Collapse

Which of the following organizational structures would be considered unorthodox?

Developers within the same team unit test each others' code prior to handing over to a separate testing team for system testing

Developers within the same team unit test each others' code prior to handing over to a separate testing team for system testing

Developers and testers are integrated within the same project team, each role focusing on a different level of testing

Developers and testers are integrated within the same project team, each role focusing on a different level of testing

After developers are done unit testing, business analysts alpha test the system before handing over to a separate testing team for system testing

After developers are done unit testing, business analysts alpha test the system before handing over to a separate testing team for system testing

DBAs confirm the referential integrity of the database and developers complete their unit testing before handing over to external organization for system testing

DBAs confirm the referential integrity of the database and developers complete their unit testing before handing over to external organization for system testing

Suggested answer: C
Explanation:

The unorthodox structure mentioned in option C involves business analysts performing alpha testing. Typically, alpha testing is conducted by internal staff or a team close to the development environment, not specifically by business analysts. This step is unusual as business analysts are generally responsible for requirements analysis and ensuring that the developed system meets business needs, rather than conducting alpha testing, which is more focused on identifying bugs and issues from a user's perspective.

ISTQB Glossary, Distributed Testing

ISTQB Advanced Level Test Manager Syllabus, Section 3.2.1

Related literature on testing roles and responsibilities

asked 18/02/2025
Jose Castillo
41 questions

Question 62

Report Export Collapse

The Test Manager must assemble team members that have which of the following characteristics?

Thrive in a routine, structured environment

Thrive in a routine, structured environment

Will not change the severity of a defect report

Will not change the severity of a defect report

Will spark informal cross training among themselves

Will spark informal cross training among themselves

Possess identical skill sets

Possess identical skill sets

Suggested answer: C
Explanation:

A test manager must assemble team members that will spark informal cross training among themselves. This means that the team members are willing and able to share their knowledge, skills, and experiences with each other, and learn from each other's feedback and suggestions. This can improve the team's performance, productivity, and quality, as well as foster a collaborative and supportive culture. Cross training can also help the team members to develop new competencies, fill skill gaps, and handle different roles and tasks when needed.Top 10 Leadership Qualities to Distinguish a Test ManagerTest manager roles and responsibilities (with FAQs)Reference:

Top 10 Leadership Qualities to Distinguish a Test Manager - Software Test Professionals

Test manager roles and responsibilities (with FAQs) - Indeed

asked 18/02/2025
Martin Ojeda Knapp
30 questions

Question 63

Report Export Collapse

Which of the following can demotivate a tester?

Receiving direct and honest feedback on areas to improve

Receiving direct and honest feedback on areas to improve

Working extra hours, resulting in a successful product deployment

Working extra hours, resulting in a successful product deployment

When metrics indicate weaknesses in their testing

When metrics indicate weaknesses in their testing

When testing is cut short, resulting in a high number of production defects

When testing is cut short, resulting in a high number of production defects

Suggested answer: D
Explanation:

This can demotivate a tester because it implies that the tester's work is not valued or respected by the management or the stakeholders. It also suggests that the tester's efforts and skills are wasted or ineffective, as the product quality is compromised and the customer satisfaction is reduced. Testing is cut short when there is insufficient time, budget, or resources allocated for testing, or when there is pressure to release the product without adequate testing. This can lead to frustration, dissatisfaction, and loss of confidence among the testers.Top 6 things that demotivate a developerHow to Demotivate Your Best EmployeesReference:

Top 6 things that demotivate a developer - Amsterdam Standard

How to Demotivate Your Best Employees - HBS Working Knowledge

asked 18/02/2025
Avtandili Tsagareishvili
47 questions

Question 64

Report Export Collapse

You are the manager of a test team. You inherited most of these people from a previous manager who promoted technical skills, particularly programming skills. As a result, your people are very strong in test automation skills, white box testing and complex test design techniques. You have just been told that you can hire five new people. You want the new people to complement the existing skill sets and you want to be sure the team will have a strong mutual respect.

Given the following options, who should you hire? [3]

Become a Premium Member for full access
  Unlock Premium Member

Question 65

Report Export Collapse

You have just conducted a skills assessment for your team. You decided to rate everyone from 1 to 5 in the skill areas as follows:

5 = expert

4 = proficient

3 = can use this skill effectively but will need some assistance

2 = interested in learning this skill but has only minimal knowledge

1 = not interested in learning this skill

Given these values, you have rated your team as shown in the table below for the designated skill areas:

ISTQB CTAL-TM image Question 65 63875516202646141056485

You will be starting to test a new product that is an upgrade from one of your existing end user products. Your testing will include white box,

performance, security, usability, and black box. You also have a goal to automate 100% of the smoke test and 50% of the regression tests by the end of the release.

Your team willingly shares knowledge and conducts regular lunch time cross-training sessions.

Your manager wants to know if you would like to bring in someone to help train your team in preparation for this project. In which area could you best utilize this help? [3]

Become a Premium Member for full access
  Unlock Premium Member

Question 66

Report Export Collapse

Following identification of a number of costly system performance failures late in the development lifecycle, your organisation has introduced a more rigorous review process for system design documents and source code to enhance phase containment. There will be subsequent checks to see if the improved review process detects/prevents these types of performance defects which are likely to have the highest impact on the technical behavior of the system. You have been tasked with evaluating the current defect management tool that will be used to support the reviews and dynamic testing, to ensure that the correct defect data attributes will be captured to enable these checks to be done.

Which three of the following attributes would be MOST effective?

a) Phase of introduction

b) Severity

c) Steps to reproduce the failure

d) Resolution details

e) Phase of detection

SELECT ONE OPTION

Become a Premium Member for full access
  Unlock Premium Member

Question 67

Report Export Collapse

Which one of the following is NOT a determining factor when considering the optimal time to conduct a document review? SELECT ONE OPTION

Become a Premium Member for full access
  Unlock Premium Member

Question 68

Report Export Collapse

You are a Test Manager at a company that develops mobile phone applications. Based on historical data in your company, you have calculated the following average metrics for system testing:

* for each 100 LOC (Lines Of Code). 4 test cases are executed

* each test case takes on average 15 minutes to execute and check

* for each 1000 LOC, 5 defects are found

You have used this information to create an estimate for the system testing of a new mobile phone application being developed to submit gas and electricity readings.

The application delivered for system testing has 50.000 lines of code. At the end of system testing, 250 defects are discovered.

Assume that:

* the system test of the new mobile phone application will require the same amount of effort as previous applications

* defect density = number of defects/1000 LOC

* no new tools or processes have been introduced to the test team

Based only on the given information, which one of the following statements is true about this new mobile phone application?

SELECT ONE OPTION

Become a Premium Member for full access
  Unlock Premium Member

Question 69

Report Export Collapse

You are the Test Manager for a software house (SoftTech), who provide a core banking product to retail banks around the world to enable their customers to process payments via the Internet and telephone banking.

Your current project is to integrate SoftTech's core banking product with Welsh Bank's existing bank systems. However, Welsh Bank's systems are maintained by experienced developers and are poorly documented.

Welsh Bank has stated that this project must comply with Financial Conduct Authority (FCA) regulatory banking standards.

A specification for the 10 interfaces to Welsh Bank's existing systems has been produced by SoftTech's development team.

You have been asked to plan and conduct reviews for the system integration and support documentation of all the systems. Which of the following is the BEST approach for this project?

SELECT ONE OPTION

Become a Premium Member for full access
  Unlock Premium Member

Question 70

Report Export Collapse

Your project manager has requested that you run management reviews in her absence. Which two of the following might you be expected to do at these reviews?

a. Check for defects in requirements documents.

b. Check the process to see if it passes the assessment.

c. Check the consistency of the project plan.

d. Check compliance by conducting evidential interviews

e. Check adequacy of management procedures.

f. Check contractual compliance for a software product Select one correct answer from the options below: