Lean had its origins in the development and practice of the ___________ Production System.

A.
Honda
A.
Honda
Answers
B.
Toyota
B.
Toyota
Answers
C.
Ford
C.
Ford
Answers
D.
Motorola
D.
Motorola
Answers
Suggested answer: B

Lean removes many forms of ______________ so Six Sigma can focus on reducing _______________.

A.
Waste, variability
A.
Waste, variability
Answers
B.
Inventory, defects
B.
Inventory, defects
Answers
C.
Waste, cost
C.
Waste, cost
Answers
D.
Movement, variation
D.
Movement, variation
Answers
Suggested answer: A

Which element of waste best describes 'the unnecessary movement of materials and/or goods'?

A.
Overprocessing
A.
Overprocessing
Answers
B.
Motion
B.
Motion
Answers
C.
Conveyance
C.
Conveyance
Answers
D.
Correction
D.
Correction
Answers
Suggested answer: C

Which element of waste best describes 'the cost of an idle resource'?

A.
Waiting
A.
Waiting
Answers
B.
Motion
B.
Motion
Answers
C.
Inventory
C.
Inventory
Answers
D.
Correction
D.
Correction
Answers
Suggested answer: A

The proper functioning of a Visual Factory is dependent upon which of these?

A.
Technically skilled workers
A.
Technically skilled workers
Answers
B.
Work space with active 5S
B.
Work space with active 5S
Answers
C.
Availability of visual tools
C.
Availability of visual tools
Answers
D.
Breakthrough projects
D.
Breakthrough projects
Answers
Suggested answer: C

Lean focuses on the sequence of activities and work required to produce a product or a service. This flow is called a ___________________.

A.
Value-add Flow
A.
Value-add Flow
Answers
B.
Production Map
B.
Production Map
Answers
C.
Value Stream
C.
Value Stream
Answers
D.
Operating Procedure
D.
Operating Procedure
Answers
Suggested answer: C

Lean Enterprise is based on the premise that anywhere work is being done which of these is also occurring?

A.
Money is being spent
A.
Money is being spent
Answers
B.
Waste is being generated
B.
Waste is being generated
Answers
C.
People are producing value added product
C.
People are producing value added product
Answers
D.
Waste is being eliminated
D.
Waste is being eliminated
Answers
Suggested answer: B

When constructing a Fishbone Diagram using the ________ approach is the most classic arrangement.

A.
6M
A.
6M
Answers
B.
4M
B.
4M
Answers
C.
5M
C.
5M
Answers
D.
Alphabetical
D.
Alphabetical
Answers
Suggested answer: A

The 5 Why Analysis is only useful if the possible independent variable can be broken down into five possible causes.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: B

The purpose of a Process Map is to identify the complexity of the process and to assist in identifying critical steps in the process.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: A