Question 41

Report Export Collapse

You are a production manager at a company which produces large batches of coffee and creamers.

After a quality inspection, batch 120008 of your cold brew coffee (item number CB-0001) was found to be too acidic and must be reworked.

You need to add 20 grams of sugar and stir the product for an additional 0.5 hours.

What three actions are required on the rework order? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Become a Premium Member for full access
  Unlock Premium Member

Question 42

Report Export Collapse

You have updated a cost category price from $5.00 to $7.00. You process a production order which uses the cost category.

After ending the order, you realize a new standard cost was not calculated after the price update.

You need to validate how this impacted the financial voucher transactions.

Which transaction would you see in the general ledger?

Become a Premium Member for full access
  Unlock Premium Member

Question 43

Report Export Collapse

A manufacturing company uses discreet manufacturing to make skateboards. Production order picking lists are manually posted after finished goods are reported as finished.

A production order has six picking lists posted. The quantities on the picking lists do not match any of the reported or finished quantities. This causes an inventory error for the raw materials. All raw material transactions must be tracked on production order and reconciled.

You need to process a single picking list for each production order.

What should you do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 44

Report Export Collapse

A customer produces light projection toys for holiday decorations throughout the year. Vendors have negotiated rebate agreements as a condition of their contact. The contract also contains the visual templates required for the customer to use in a season.

Vendor rebate agreements must only be applied if the following requirements are met:

Units of measure for deliverables are the same unit of measure as on the agreement The agreement is valid as of the date a purchase order is generated

You need to configure the vendor rebate agreements.

What should you do?

Become a Premium Member for full access
  Unlock Premium Member

Question 45

Report Export Collapse

A paint manufacturer is using Process manufacturing. The manufacturer has a quality error. Batches of paint that use the wrong formula have been marked for rework.

The production planner reports they cannot schedule the batch order even though the order has been estimated.

You need to add reservations to the items to be used for the rework order.

What should you do?

Become a Premium Member for full access
  Unlock Premium Member

Question 46

Report Export Collapse

You are the lead product design engineer at a plastics manufacturing company. You implement a new process that uses a single tool to produce three finished goods at the same time.

You need to set up the planning item number and formula to correctly to manufacture the three items.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Become a Premium Member for full access
  Unlock Premium Member

Question 47

Report Export Collapse

A company produces homeopathic lotions for pain relief and uses Dynamics 365 Supply Chain Management. You have replaced the vendor of a product's active ingredient with a new vendor. The new vendor is supplying the ingredient at a higher concentration of 25 percent.

The previous vendor concentration was 15 percent. You are consistently running out of two of the complimentary ingredients.

You need to update the formula and ingredient settings to allow for better order planning.

What should you do?

Become a Premium Member for full access
  Unlock Premium Member

Question 48

Report Export Collapse

You are the production scheduler at a manufacturing company. The company is not using advanced warehousing.

You have firmed a planned production order from master planning. The order is ready to be processed.

You now need to process the order in production control.

What should you do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 49

Report Export Collapse

A company produces various products using Process manufacturing.

The manufacturer makes two co-products from a formula and rarely produces the primary formula item. The costs of making the co-products are inflated. The manufacturer must update the costs of producing the co-products and change the formula to not produce the primary formula item.

You need to change the primary formula item type.

What should you do?

Become a Premium Member for full access
  Unlock Premium Member

Question 50

Report Export Collapse

A chemical manufacturing company uses Dynamics 365 Supply Chain Management. A batch of material has a quality issue and must be reworked.

You need to create the rework order the production.

Which three options must be set? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Become a Premium Member for full access
  Unlock Premium Member