PMI PgMP Practice Test - Questions Answers, Page 30

List of questions
Question 291

What actions are taken in the process of developing and maintaining a program risk register?
Question 292

A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program.
As a result, the program manager must do which of the following?
Question 293

An aircraft manufacturer is engaged by an airline to build a fleet of new airliners. The program charter has been approved, but the stakeholders are concerned that the delivery method of the program may not meet their expectations.
Using the program master schedule, what will the program manager incorporate to align the program with the expectations of the stakeholders?
Question 294

A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results?
Question 295

The program manager defines the program objectives, requirements, and develops a high-level road map. To ensure program alignment with the enterprise strategic plan, the program manager should work with which of the following?
Question 296

A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.
What is the program manager's next step?
Question 297

A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project.
What should the program manager do next?
Question 298

A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation timeline.
What key elements should be included in the benefits register to achieve this goal?
Question 299

A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?
Question 300

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million.
Since the shutdown was not anticipated, what should the program manager do first?
Question