A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
Change log
Issue log
Risk register
Defect log
A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?
IaaS
XaaS
DaaS
SaaS
Which of the following statements best describes zero-based budgeting?
Start with the budget from the last project and add any new expenses.
Start with allocating expenses based on the importance of the project.
Start the project with a fixed amount decided by the management team.
Start with no financial plan and justify each new expense.
Which of the following is a quantitative key performance indicator?
The project sponsor ranked the graphics of an application as four out of five.
The project implements the application in ten different geographical regions.
The workers complete tasks on average 25% faster using a new application.
The use of a multimedia interface appeals more to users under the age of 21.
Which of the following activities should a project manager perform during the closing phase? (Select three)
Lessons learned
Risk analysis
Removing resources
Acquiring resources
Statement of work sign-off
Stakeholder analysis
Removing access
Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?
Concept of operations
WBS
Integrated master schedule
RACI
During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?
Status report
Issue log
Risk report
Risk register
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?
Risk
Change
Defect
Issue
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
Validation check
Downtime window schedule
Customer notifications
Risk analysis
Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?
Exploit
Share
Transfer
Accept