PMI PMI-ACP Practice Test - Questions Answers, Page 10
List of questions
Question 91
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient.
What should the project team have done prior to product release?
Question 92
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During a daily stand up meeting, a developer expresses concerns that the selected technology limits the number of concurrent users. What should the agile team lead do?
Question 93
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During a team meeting, members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks, which has lowered motivation. What should the agile practitioner do?
Question 94
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?
Question 95
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During planning sessions, an agile practitioner notices that some team members do not share common ideas. What should the agile practitioner do?
Question 96
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
The executive leadership wants to understand ways to better deliver on time and on budget. What can the project team do to assist in achieving the organizational goal?
Question 97
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.
What should the product owner do next?
Question 98
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments. What should the agile coach do?
Question 99
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?
Question 100
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?
Question