PMI PMI-ACP Practice Test - Questions Answers, Page 17
List of questions
Related questions
An agile team is planning the next iteration tor a product release that has accumulated technical debt What should the team do?
Team A is working on the second sprint of a product release Team B. which is an interdependent team located on the same floor requires extensive and frequent information to complete its sprint goal What should the agile team lead do?
A product owner asks a newly formed scrum team how many story points will be completed m a sprint What should the scrum master do?
During a review session an agile team presented done requirements to a group of stakeholders Stakeholder feedback indicated that the done requirements failed to meet the most pressing needs and provide value What should the team have done to prevent this?
During project inception an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision The stakeholder asks for detailed requirements design, and delivery plans What should the agile practitioner do?
During a project meeting a team is laced with a difficult decision After discussion and deliberation the project leader makes the final decision and ends the discussion This causes a team member to withdraw from future collaboration How could (he project leader have avoided this?
A legal department representative contacts the scrum master because white the projects budget has been maintained it has exceeded its original contracted time and scope. What should the scrum master do?
An experienced product owner presents the epics and corresponding stones during a release planning session with the established team The executive sponsor asks the team when the features will he delivered What should the agile team do?
During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stones into the iteration backlog What should the team do first to define the tasks needed to implement the user stories?
Outing a review session a customer representative is concerned that a story fails to satisfy the scope of work. However the product owner declares that the scope of work is complete What should be done with this story?
Question