During a planning session, four out of five team members vole to include eight story points m a particular story, while the fifth member votes for five story points How should this be handled7
Two similar stories A and B. are estimated at 3 story points Story C. is estimated a( 8 points Alter an iteration in which A and C were completed it is found that story A took much longer than story C.
What should the agile practitioner do?
An agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released What should the agile team do?
An organization initiates a pilot project to introduce agile methodology for the successful delivery of projects. What should the project manager do to share this project's knowledge and learning with wider organizational business groups?
A projects first iteration contains item
A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete m the marketplace1. What analysis should the team use to understand the issues?
More details for a story are required before the upcoming sprint planning meeting. What should the scrum master do?
A member of the development team is working on a prioritized non-functional requirement involving integrating with a 3rd party system This integration has not been done before on the project.
What should the project leader suggest?
During the review session, the product owner discovers that the user interface has a response time of 10 seconds The non-functional requirements state that it should respond in less than two seconds.
The team complains that this requirement was not communicated to them.
What should have been done to avoid this?
What should a learn do when they complete ail sprint goals earlier than expected?
Question