PMI PMI-ACP Practice Test - Questions Answers, Page 7
List of questions
Question 61

What should a team consider when calculating the effort needed to complete a product backlog?
Question 62

A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?
Question 63

A team is transitioning from a predictive approach to an agile approach. Historically, the team has delivered work products that did not meet customer expectations. What agile practice can help the team to alleviate this?
Question 64

While attending a conference, an agile practitioner learns of a new user interface (Ul) framework that could benefit the team. What should the agile practitioner do next?
Question 65

How can an agile team working on a new product ensure alignment with external stakeholders?
Question 66

A team identifies the number of threats and lists them in the order in which they were identified.
After analyzing a cause-and-effect diagram, the ownership of the threats and their treatment is assigned, and a number of risk cards are placed on the Kanban board.
What approach should be used to manage these threats?
Question 67

A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate.
What should the agile project leader do?
Question 68

An executive requests information regarding a sprint status. What action should the product owner take?
Question 69

While reviewing the sprint burn down during a stand up. the scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.
What should the scrum team do?
Question 70

How can a scrum team obtain more feedback from a minimally responsive outside stakeholder?
Question