ExamGecko
Home / PMI / PMI-RMP / Practice Test 4
Ask Question

PMI PMI-RMP Practice Test 4

Add to Whishlist
00:00:00
Show Answer
Report Issue   Restart test

Question 1 / 40

A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

Become a Premium Member for full access
  Unlock Premium Member