ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 2

Question list
Search
Search

List of questions

Search

Related questions











An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

A.

Add only the threats to the risk register

A.

Add only the threats to the risk register

Answers
B.

Utilize different tools to identify the risks

B.

Utilize different tools to identify the risks

Answers
C.

Plan risk responses to the threats

C.

Plan risk responses to the threats

Answers
D.

Update the risk register with the identified risks

D.

Update the risk register with the identified risks

Answers
Suggested answer: D

Explanation:

The risk manager should update the risk register with both the opportunities and threats identified during the SWOT analysis. This will help in tracking and managing all potential risks throughout the project lifecycle.

Update the risk register with the identified risksComprehensive and Detailed Explanation:According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain ofRisk Identificationis to update the risk register with identified risks, causes, categories, and potential responses1.A risk register is a document used to track and report on project risks and opportunities throughout the project's life cycle2. In this scenario, the risk manager should update the risk register with the identified risks, both opportunities and threats, that result from the SWOT analysis. The risk manager should also include the causes, categories, and potential responses for each risk, as well as other relevant information such as probability, impact, priority, owner, etc.The risk manager should not add only the threats to the risk register, because opportunities are also a type of risk that can have a positive effect on the project objectives and should be recorded and managed accordingly3.The risk manager should not utilize different tools to identify the risks, because the SWOT analysis is a valid and useful tool for risk identification and there is no indication that it was insufficient or inappropriate for the project context4.The risk manager should not plan risk responses to the threats, because that is a separate process that comes after risk identification and requires further analysis and evaluation of the risks5.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 82: Risk Register in Project Management - Project Management Academy63: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 3974: How to Perform a SWOT Analysis - Project Risk Coach25: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 440.

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

A.

US$68,000

A.

US$68,000

Answers
B.

US$52,000

B.

US$52,000

Answers
C.

US$120,000

C.

US$120,000

Answers
D.

US$80,000

D.

US$80,000

Answers
Suggested answer: B

Explanation:

In risk management, to calculate the contingency budget for risks, we use the Expected Monetary Value (EMV) formula: EMV=ProbabilityofRiskImpactofRisk\text{EMV} = \text{Probability of Risk} \times \text{Impact of Risk}EMV=ProbabilityofRiskImpactofRisk

For Risk A:

Probability: 40% or 0.40

Impact: US$100,000 \text{EMV of Risk A} = 0.40 \times 100,000 = US$40,000

For Risk B:

Probability: 60% or 0.60

Impact: US$20,000 \text{EMV of Risk B} = 0.60 \times 20,000 = US$12,000

Total contingency budget = EMV of Risk A + EMV of Risk B 40,000 + 12,000 = US$52,000

Thus, the total contingency budget required for both risks is US$52,000. This approach follows PMI's risk management guidelines, specifically under the 'Quantitative Risk Analysis' process. This process focuses on determining numerical probabilities and monetary impacts to compute the expected financial impact of identified risks.

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

A.

Highlight this situation to the project manager

A.

Highlight this situation to the project manager

Answers
B.

Conduct a cost-benefit analysis

B.

Conduct a cost-benefit analysis

Answers
C.

Change the risk response strategy

C.

Change the risk response strategy

Answers
D.

Analyze the situation and meet with the risk owner

D.

Analyze the situation and meet with the risk owner

Answers
Suggested answer: D

Explanation:

The first thing the risk manager should do is analyze the situation and meet with the risk owner. This will allow the risk manager to understand the challenges faced by the risk owner and work with them to find a solution. Conducting a cost-benefit analysis or changing the risk response strategy may be necessary, but it is important to first understand the situation before taking any action.

According to the PMI-RMP Exam Content Outline, one of the tasks in the domain of Risk Response Planning is to ''assist the risk owners in developing and implementing risk response strategies and actions based on the agreed-upon risk response plan''. Therefore, the first thing the risk manager should do is to analyze the situation and meet with the risk owner to understand the root cause of the challenges and the cost overrun, and to discuss possible solutions or alternatives. Highlighting this situation to the project manager, conducting a cost-benefit analysis, or changing the risk response strategy are possible actions that can be taken after the analysis and meeting, but not before.Reference: PMI-RMP Exam Content Outline, Domain 3: Risk Response Planning, Task 31

The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?

A.

Quantitative risk analysis

A.

Quantitative risk analysis

Answers
B.

Force field analysis

B.

Force field analysis

Answers
C.

Qualitative risk analysis

C.

Qualitative risk analysis

Answers
D.

Stakeholder analysis

D.

Stakeholder analysis

Answers
Suggested answer: C

Explanation:

The analysis currently being used is qualitative risk analysis. Qualitative risk analysis involves assessing risks based on their likelihood of occurrence and their potential impact on the project. This type of analysis can help identify biases that may be impacting how team members perceive risks.

Qualitative risk analysis is the process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics. Qualitative risk analysis helps to identify the most significant risks that require attention and response planning. One of the tools and techniques used in qualitative risk analysis is risk data quality assessment, which evaluates the degree to which the data about individual project risks is useful for risk management. Risk data quality assessment considers various aspects of data quality, such as reliability, accuracy, integrity, precision, and bias. Bias is the tendency of human judgment to be influenced by personal or organizational preferences, assumptions, beliefs, or emotions, rather than by objective facts or evidence. Bias can affect how project team members perceive and assess risks, leading to inaccurate or incomplete risk analysis results. Therefore, the risk manager who realizes the project team members have biases impacting how they perceive risks is currently using qualitative risk analysis to prioritize the risks and assess the quality of risk data.Reference:PMI, Practice Standard for Project Risk Management, 2009, p. 37-38, 41-42.

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

A.

Prompt lists

A.

Prompt lists

Answers
B.

Interviews

B.

Interviews

Answers
C.

Delphi technique

C.

Delphi technique

Answers
D.

Nominal group technique

D.

Nominal group technique

Answers
Suggested answer: D

Explanation:

The risk identification technique that the risk manager should use is the nominal group technique. This technique involves bringing stakeholders together to brainstorm potential risks and then ranking them based on their importance. This allows for interaction and collaboration among stakeholders, which can help ensure that an exhaustive list of risks is created.

The nominal group technique is a risk identification technique that involves the interaction and collaboration of stakeholders to generate an exhaustive list of risks. It is a structured process that allows each participant to share their ideas independently, then rank and prioritize them as a group.This technique ensures that all opinions are considered and reduces the influence of dominant or biased individuals12

.

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

A.

Suspend the project as the secondary risk will negatively impact residents' health which is not acceptable.

A.

Suspend the project as the secondary risk will negatively impact residents' health which is not acceptable.

Answers
B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

Answers
C.

Assess and record associated secondary risks and proceed to treat them as any other risks.

C.

Assess and record associated secondary risks and proceed to treat them as any other risks.

Answers
D.

Proceed with the project as normal since a minor number of residents will be effected negatively.

D.

Proceed with the project as normal since a minor number of residents will be effected negatively.

Answers
Suggested answer: C

Explanation:

The project manager should assess and record associated secondary risks and proceed to treat them as any other risks. This involves identifying and evaluating the potential negative health effects of using pesticides and developing a plan to mitigate these risks. While it is important to consider the concerns of residents, the health authorities have determined that not moving forward with the plan will have more serious consequences on public health.

Secondary risks are those that arise as a direct outcome of implementing a risk response. In this case, the use of pesticides is a risk response to limit the risks of harmful insects, but it may also cause negative health effects to some residents. This is a secondary risk that needs to be assessed and recorded in the risk register, along with its probability, impact, and response plan. The project manager should not suspend the project, as this would ignore the primary risk of harmful insects. The project manager should not consult with health experts to provide a risk trigger, as this is not a valid risk management technique. A risk trigger is an indication that a risk event is about to occur or has occurred, not a condition that prevents a risk response from being implemented. The project manager should not proceed with the project as normal, as this would neglect the secondary risk and its potential consequences. The project manager should follow the risk management process and treat the secondary risk as any other risk in the project.Reference:PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition. Chapter 11: Project Risk Management, p. 408. 5

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

A.

Ask the team to perform an earned value analysis.

A.

Ask the team to perform an earned value analysis.

Answers
B.

Review the lessons learned from other projects.

B.

Review the lessons learned from other projects.

Answers
C.

Ask the team to prepare a Monte Carlo analysis.

C.

Ask the team to prepare a Monte Carlo analysis.

Answers
D.

Ask the risk expert to perform a PESTLE evaluation.

D.

Ask the risk expert to perform a PESTLE evaluation.

Answers
Suggested answer: C

Explanation:

The action that the risk manager should propose is to ask the team to prepare a Monte Carlo analysis. This is a statistical technique that can be used to model the probability of different outcomes in a project. By performing a Monte Carlo analysis, the project manager can objectively evaluate key project risks and develop response plans based on this analysis.

A Monte Carlo analysis is a simulation technique that uses probability distributions and random sampling to model the possible outcomes of a project risk event. It can help the project manager to evaluate the key project risks and develop response plans based on the expected value, standard deviation, and confidence intervals of the results. A Monte Carlo analysis can also provide information on the probability of achieving the project objectives, such as cost, schedule, and quality.A Monte Carlo analysis is an objective method because it does not rely on subjective judgments or opinions, but on mathematical calculations and statistical data.Reference: PMBOK Guide, 6th edition, Section 11.5.2.3, Monte Carlo Analysis1

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.

A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.

Answers
B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.

B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.

Answers
C.

Before a formal bid response is provided to the client to gain a greater understanding of the project's risk profile.

C.

Before a formal bid response is provided to the client to gain a greater understanding of the project's risk profile.

Answers
D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.

D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.

Answers
Suggested answer: C

Explanation:

A risk register should be developed before submitting a formal bid response to help the company understand the project's risk profile and account for potential risks in their proposal. This allows the company to make informed decisions about cost, schedule, and resources. (Reference: Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, Section 11.2)

A risk register is a document that is used as a risk management tool to identify potential setbacks within a project.A risk register is typically created at the start of a project (before it begins), and is regularly referenced and updated throughout the life of a project through deliberate risk monitoring and control1. A risk register is an important component of any successful risk management process and helps mitigate potential project delays that could arise.A risk register is shared with project stakeholders to ensure information is stored in one accessible place2. A risk register also helps to establish a hierarchy of risks, starting with the most impactful. The goal should be to have a path to mitigating those risks, reducing the harm they cause, or eliminating them.The register should also outline what's considered an acceptable level of risk and how to set up insurance to help offset the impacts3. Therefore, a risk register should be developed before a formal bid response is provided to the client to gain a greater understanding of the project's risk profile. This will help to estimate the project costs, schedule, and scope more accurately and realistically, as well as to identify the contingency plans and reserves needed to deal with the potential risks.Developing a risk register during the project execution phase, when a client project kick-off meeting is held, or after a project budget is set up with a purchase order are all too late to effectively identify and manage the risks that could affect the project success.Reference:2,3,1,4

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

A.

The audit team

A.

The audit team

Answers
B.

The risk manager

B.

The risk manager

Answers
C.

The risk owners

C.

The risk owners

Answers
D.

The discipline engineers

D.

The discipline engineers

Answers
Suggested answer: B

Explanation:

The risk manager is responsible for ensuring that all risks, including secondary risks, are identified and addressed during the risk response planning process. If key secondary risks were missed, the risk manager should be held accountable. (Reference: Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, Section 11.5)

The risk manager is responsible for identifying and analyzing risks, as well as planning and implementing risk responses. Secondary risks are those risks that arise as a direct result of implementing a risk response to a specific risk. The risk manager should have considered the potential secondary risks during the risk response planning and updated the risk register accordingly.The project manager should hold the risk manager accountable for missing the secondary risks and ensure that they are properly addressed12

.

A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)

A.

Budget variance data from previously completed projects.

A.

Budget variance data from previously completed projects.

Answers
B.

Project scope and cost management plans from previous projects.

B.

Project scope and cost management plans from previous projects.

Answers
C.

Lessons learned from similar completed projects.

C.

Lessons learned from similar completed projects.

Answers
D.

Previous project risks that may be relevant to this project.

D.

Previous project risks that may be relevant to this project.

Answers
E.

Stakeholder analysis metrics from projects with similar risk profiles.

E.

Stakeholder analysis metrics from projects with similar risk profiles.

Answers
Suggested answer: C, D

Explanation:

A risk checklist is a tool for identifying risks based on historical information and knowledge from similar projects. It is a list of potential risk sources or categories that can be used to prompt the project team to consider possible risks that may affect the project. A risk checklist should include information that is relevant and useful for identifying risks, such as lessons learned from similar completed projects and previous project risks that may be relevant to this project. These two pieces of information can help the project manager to learn from past experiences and avoid repeating the same mistakes or overlooking the same threats or opportunities. A risk checklist should not include information that is not directly related to risk identification, such as budget variance data from previously completed projects, project scope and cost management plans from previous projects, or stakeholder analysis metrics from projects with similar risk profiles. These pieces of information may be useful for other aspects of project management, such as planning, monitoring, or controlling, but they are not helpful for identifying risks on a project.Reference:PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition. Chapter 11: Project Risk Management, p. 397. 5

Lessons learned and previous project risks are valuable sources of information for creating a risk checklist. They provide insights into potential risks that may impact the current project and help the project manager develop appropriate risk responses. Budget variance data, project scope and cost management plans, and stakeholder analysis metrics, although useful, are not directly related to risk identification. (Reference: Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, Section 11.2)

Total 201 questions
Go to page: of 21