PMI PMI-RMP Practice Test - Questions Answers, Page 2
List of questions
Related questions
An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.
What should the risk manager do next?
Add only the threats to the risk register
Utilize different tools to identify the risks
Plan risk responses to the threats
Update the risk register with the identified risks
As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.
What is the total contingency budget that should be created?
US$68,000
US$52,000
US$120,000
US$80,000
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?
Highlight this situation to the project manager
Conduct a cost-benefit analysis
Change the risk response strategy
Analyze the situation and meet with the risk owner
The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?
Quantitative risk analysis
Force field analysis
Qualitative risk analysis
Stakeholder analysis
A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.
Which risk identification technique should the risk manager use?
Prompt lists
Interviews
Delphi technique
Nominal group technique
In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.
How should the project manager address this concern with the health authorities?
Suspend the project as the secondary risk will negatively impact residents' health which is not acceptable.
Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.
Assess and record associated secondary risks and proceed to treat them as any other risks.
Proceed with the project as normal since a minor number of residents will be effected negatively.
The project manager wants to use an objective method to evaluate the key project risks and develop response plans.
What action should the risk manager propose?
Ask the team to perform an earned value analysis.
Review the lessons learned from other projects.
Ask the team to prepare a Monte Carlo analysis.
Ask the risk expert to perform a PESTLE evaluation.
A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?
During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.
When a client project kick-off meeting is held to introduce risk assessment process to the client.
Before a formal bid response is provided to the client to gain a greater understanding of the project's risk profile.
After a project budget is set up with a purchase order to charge hours for a risk workshop.
A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.
Who should the project manager hold accountable for missing the risks?
The audit team
The risk manager
The risk owners
The discipline engineers
.
A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)
Budget variance data from previously completed projects.
Project scope and cost management plans from previous projects.
Lessons learned from similar completed projects.
Previous project risks that may be relevant to this project.
Stakeholder analysis metrics from projects with similar risk profiles.
Question