PMI PMI-RMP Practice Test - Questions Answers, Page 6
List of questions
Related questions
A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?
US$20.000 loss
US$20,000 profit
US$40,000 loss
US$100,000 profit
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from happening?
Reformed the risk monitoring and closing process properly.
Created the project work plan and budget more accurately.
Educated the project team on budget change requests.
Communicated better with the organization's CEO.
The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.
What should the project risk manager do next to identify risks?
Review the risk breakdown structure to ensure project scope is covered.
Use the brainstorming technique to remove personal bias.
Use expert judgment to remove ego or emotional conflict.
Consider the Delphi technique to gather all stakeholder opinions.
A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges
What two actions should the risk owner take? (Choose two.)
Implement the secondary risk response and update the project documents.
Conduct meeting with all stakeholder to agree on post impact solutions.
Set the corresponding trigger conditions to the secondary risk.
Engage the project manager to authorize the secondary risk's response.
Update and communicate assessments of the secondary risk's impact.
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.
What should the project manager do next?
Review assumptions and constraints around risks.
Develop the risk response plans for identified risks.
Determine the likelihood and impact of the risks.
Apply an iterative approach to risk identification.
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
How should the risk manager proceed?
Perform a qualitative risk analysis and update the results.
Update the assumptions/exclusions register with the new information.
Update the risk register and prepare for the Monte Carlo analysis.
Perform a quantitative risk analysis and update the results.
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.
What should the project manager do first?
Include the risk in the register and communicate with the stakeholders.
Communicate with the client to provide the previous shutdown plan.
Review and update the project schedule.
Interview the other project manager to learn more details.
The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.
How should the project manager and the risk manager handle this situation?
Ensure the project complies with the current traffic regulations and laws.
Send a letter to the traffic authority with the general project information.
Perform inquiries on the website of the traffic authority weekly.
Meet with the traffic authority staff in charge of the new regulation.
The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.
What should the project manager do?
Implement the risk response strategies into the risk plan.
Inform the sponsor that these risks should be added according to experience.
Add the risks to the risk register and determine a contingency.
Discuss and evaluate the identified risks with the project team.
During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.
What should the risk manager do to handle this situation?
Revisit this risk in the risk register and redefine the mitigation strategy.
Activate the contingency plan to handle this risk during execution.
Mark this new risk as an extremely high priority and inform all stakeholders.
Ask the project sponsor for more budget to deal with this risk.
Question