PMI PMP Practice Test - Questions Answers, Page 148
List of questions
Question 1471
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
DRAG DROP
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
Question 1472
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
DRAG DROP
A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.
Drag each stakeholder scenario on the left to the correct engagement level on the right.
Question 1473
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project team has recently finished a sprint for developing two features for a fleet management system. Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to what has occurred.
What can the project manager do to help increase the team's motivation and engagement with the project?
Question 1474
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
Question 1475
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A highly skilled team resource received a job offer and is leaving the project soon. What should the project manager do to maintain project performance while a new team member is being onboarded?
Question 1476
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk materialized and the project time line had to be extended by 2 months.
Which two actions should the project manager take? (Choose two.)
Question 1477
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter.
Several thousand machines will be impacted by this change.
What should the project manager do first?
Question