PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 44
List of questions
Related questions
Question 431

Which is a description of a purpose of the communication management approach?
Question 432

Which TWO are objectives of the 'managing a stage boundary' process?
1. To confirm to the project board that there are no products outstanding for the stage
2. To ensure that expectations are managed via accurate reporting to the project manager during a stage
3. To ensure that the project management team is not distracted by delivering additional products during the stage
4. To request the project board to approve work to start on the next stage
Question 433

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.
Which management product should the project manager produce?
Question 434

When does the 'directing a project' process start?
Question 435

Which TWO are objectives of the 'starting up a project' process?
1. To provide an interface between the corporate layer and the project
2. To provide the required authority to initiate the project
3. To plan the work required for project initiation
4. To provide business justification for initiating the project
Question 436

When is a work breakdown structure MOST useful?
Question 437

What is a description of a purpose of the 'quality' practice?
Question 438

Which statement about capability and competency within a project is CORRECT?
Question 439

The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.
In which step of the 'issue management technique should the change authority request this information?
Question 440

Which is a description of a purpose of the 'managing product delivery' process?
Question