Which is an objective of the Directing a Project process?

Create and authorize the project mandate
Create and authorize the project mandate
Provide management control and direction
Provide management control and direction
Control the day-to-day running of the project
Control the day-to-day running of the project
Provide accurate progress information to the Project Manager
Provide accurate progress information to the Project Manager
Suggested answer: B

Explanation:

An objective of the Directing a Project process is to provide management control and direction for the project. This involves making strategic decisions, providing overall guidance to the Project Manager, and ensuring the project remains aligned with organizational objectives and capable of delivering the benefits defined in the Business Case.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Penny Chang
47 questions

Question 62

Report
Export
Collapse

In what process is the authorization to deliver the project's products given?

Starting up a Project
Starting up a Project
Initiating a Project
Initiating a Project
Managing a Stage Boundary
Managing a Stage Boundary
Directing a Project
Directing a Project
Suggested answer: D

Explanation:

The authorization to deliver the project's products is given during the Directing a Project process. This process involves the Project Board's decision-making responsibilities, including granting permission to proceed with the project after the initiation phase and authorizing the delivery of stages as the project progresses.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Miguel Pinar Guruceta
43 questions

Question 63

Report
Export
Collapse

Who should act as the communication channel between a project and corporate or programme management?

Project Board
Project Board
Project Assurance
Project Assurance
Project Manager
Project Manager
Project Support
Project Support
Suggested answer: A

Explanation:

The Project Board acts as the primary communication channel between a project and corporate or programme management. This role involves ensuring that the project aligns with corporate objectives, communicating the needs and constraints of the project to higher management, and securing necessary resources and support.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
John Johnson
29 questions

Question 64

Report
Export
Collapse

Which statement about the Directing a Project process is true?

Provides a mechanism for the Project Board to assure that there is continued business justification
Provides a mechanism for the Project Board to assure that there is continued business justification
Covers the day-to-day activities of the Project Manager
Covers the day-to-day activities of the Project Manager
Ensures there are regular progress meetings
Ensures there are regular progress meetings
Begins on completion of the Initiating a Project process
Begins on completion of the Initiating a Project process
Suggested answer: A

Explanation:

The Directing a Project process in PRINCE2 provides the Project Board with a mechanism to ensure there is continued business justification for the project throughout its lifecycle. This process is crucial for maintaining the project's alignment with organizational objectives and for making decisions at key points such as stage boundaries.

Reference: PRINCE2 Foundation official documentation and study materials.

asked 23/09/2024
Joyce Ann Devilles
41 questions

Question 65

Report
Export
Collapse

Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Only 1 is true
Only 1 is true
Only 2 is true
Only 2 is true
Both 1 and 2 are true
Both 1 and 2 are true
Neither 1 or 2 are true
Neither 1 or 2 are true
Suggested answer: C

Explanation:

Both statements about the Project Initiation Documentation (PID) are correct. The PID is essential for establishing a solid foundation for the project, ensuring that all stakeholders agree on the project's objectives and how it will be managed before the Project Board authorizes it. Additionally, the PID should be updated at the end of each stage to reflect the current status of the project, ensuring that it continues to meet the project's requirements and objectives.

Reference: PRINCE2 Foundation official documentation and study materials.

asked 23/09/2024
Baljit Bhadare
39 questions

Question 66

Report
Export
Collapse

Which is an objective of the Initiating a Project process?

Develop the corporate quality management system as part of the Project Initiation Documentation
Develop the corporate quality management system as part of the Project Initiation Documentation
Prepare the plans for the subsequent stages
Prepare the plans for the subsequent stages
Summarize how the organization's project management method will be tailored for the project
Summarize how the organization's project management method will be tailored for the project
Request authority from corporate management to deliver the project
Request authority from corporate management to deliver the project
Suggested answer: C

Explanation:

One of the key objectives of the Initiating a Project process is to tailor the organization's project management method to suit the specific requirements of the project. This involves adapting processes, controls, roles, responsibilities, and techniques to ensure they are appropriate for the project's context.

Reference: PRINCE2 Foundation official documentation and study materials.

asked 23/09/2024
Wellington Rodrigues da Costa
34 questions

Question 67

Report
Export
Collapse

Which is NOT a purpose of the Initiating a Project process?

Enable a Project Board decision about the commitment of resources to a project
Enable a Project Board decision about the commitment of resources to a project
Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
Establish solid foundations for a project
Establish solid foundations for a project
Enable the Project Board to decide whether it is worthwhile to initiate a project
Enable the Project Board to decide whether it is worthwhile to initiate a project
Suggested answer: D

Explanation:

This statement is not true as the purpose of the Initiating a Project process. The correct purpose of this process is to ensure that there are solid foundations for the project, usually after the project has already been decided as worthwhile and approved for initiation. The decision to initiate a project is typically made before the Initiating a Project process.

Reference: PRINCE2 Foundation official documentation and study materials.

asked 23/09/2024
Meghan Crofford
39 questions

Question 68

Report
Export
Collapse

Which plan provides the Business Case with costs during the Initiating a Project process?

Initiation Stage Plan
Initiation Stage Plan
Project Plan
Project Plan
Stage Plan
Stage Plan
Team Plan
Team Plan
Suggested answer: B

Explanation:

During the Initiating a Project process in PRINCE2, the Project Plan provides the Business Case with necessary details, including cost estimates. This plan outlines the overall scope and timing of the project and sets the baseline for project management activities, including cost control.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
WONG CHUN KIT WONG CHUN KIT
28 questions

Question 69

Report
Export
Collapse

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

Project Brief
Project Brief
Project Initiation Documentation
Project Initiation Documentation
Project mandate
Project mandate
Benefits Review Plan
Benefits Review Plan
Suggested answer: B

Explanation:

The Project Initiation Documentation (PID) is the base product against which the Project Board can assess progress, issues, and ongoing viability questions in PRINCE2. The PID includes key documents such as the Business Case, the Project Plan, and risk management information, providing a comprehensive reference for governance decisions throughout the project.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Mark Chow
43 questions

Question 70

Report
Export
Collapse

Why is the Initiating a Project process used?

To decide which project approach is suitable for the project
To decide which project approach is suitable for the project
To fully understand how the project objectives will be achieved before committing significant resources
To fully understand how the project objectives will be achieved before committing significant resources
To produce the required Work Packages
To produce the required Work Packages
To enable corporate or programme management to give authorization to deliver a project
To enable corporate or programme management to give authorization to deliver a project
Suggested answer: B

Explanation:

The Initiating a Project process is used in PRINCE2 to ensure that there is a thorough understanding of how the project's objectives will be achieved, which includes a definition of the project's scope, benefits, risks, and approach before significant resources are committed. This process helps in establishing a clear and shared understanding of the project's basis before moving forward.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Frederik Pardon
36 questions
Total 463 questions
Go to page: of 47