What term is used to describe boards that display what work needs to be completed for people working on a project?

A.
Work in progress limit
A.
Work in progress limit
Answers
B.
Information radiator
B.
Information radiator
Answers
C.
Highlight report
C.
Highlight report
Answers
D.
Glad! Sad! Mad!
D.
Glad! Sad! Mad!
Answers
Suggested answer: C

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_190&showNav=true&expandNav=true

Which two statements about tailoring the business case in an agile environment are CORRECT?

A.
It should be unnecessary because products of the highest value will be delivered first.
A.
It should be unnecessary because products of the highest value will be delivered first.
Answers
B.
It should identify the minimum viable product and when it will be delivered.
B.
It should identify the minimum viable product and when it will be delivered.
Answers
C.
It should take into account that the scope may be reduced during the course of the project.
C.
It should take into account that the scope may be reduced during the course of the project.
Answers
D.
It should show the features, the order in which they will be delivered and any dependencies.
D.
It should show the features, the order in which they will be delivered and any dependencies.
Answers
E.
1 and 2
E.
1 and 2
Answers
F.
2 and 3
F.
2 and 3
Answers
G.
3 and 4
G.
3 and 4
Answers
H.
1 and 4
H.
1 and 4
Answers
Suggested answer: B

What should the business case state about the minimum viable product (MVP)?

A.
When the MVP will be defined
A.
When the MVP will be defined
Answers
B.
That the MVP must go into operational use
B.
That the MVP must go into operational use
Answers
C.
What the MVP is
C.
What the MVP is
Answers
D.
That the MVP is the same as project viability
D.
That the MVP is the same as project viability
Answers
Suggested answer: B

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_56&showNav=true&expandNav=true

How does the change theme regard change in PRINCE2 Agile?

A.
As disruptive
A.
As disruptive
Answers
B.
As something to be avoided
B.
As something to be avoided
Answers
C.
As a necessity
C.
As a necessity
Answers
D.
As inevitable
D.
As inevitable
Answers
Suggested answer: D

Explanation:

Reference: https://edward-designer.com/web/prince2-foundation-notes-change-theme/

Which statement about the ‘keep teams stable’ target is CORRECT?

A.
It applies primarily to the long term, such as a project or a program
A.
It applies primarily to the long term, such as a project or a program
Answers
B.
It is the primary reason why the tolerance for cost is set to zero
B.
It is the primary reason why the tolerance for cost is set to zero
Answers
C.
It prevents compromising the overall quality level of the product
C.
It prevents compromising the overall quality level of the product
Answers
D.
It results in the early delivery of a minimum viable product
D.
It results in the early delivery of a minimum viable product
Answers
Suggested answer: B

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41

What needs to happen when new detailed requirements are added to a timebox?

A.
Requirements of a similar level of effort should be removed
A.
Requirements of a similar level of effort should be removed
Answers
B.
More people should be added to the delivery team
B.
More people should be added to the delivery team
Answers
C.
The delivery milestones should be reviewed and re-planned
C.
The delivery milestones should be reviewed and re-planned
Answers
D.
Formal change control should be applied
D.
Formal change control should be applied
Answers
Suggested answer: A

Which statement about the ‘accept that the customer doesn’t need everything’ target is correct?

A.
It gives confidence on the progress of the project
A.
It gives confidence on the progress of the project
Answers
B.
It can result in the early delivery of a minimum viable product
B.
It can result in the early delivery of a minimum viable product
Answers
C.
It allows misunderstandings to be dealt with appropriately
C.
It allows misunderstandings to be dealt with appropriately
Answers
D.
It is achieved by managing the culture of the team carefully
D.
It is achieved by managing the culture of the team carefully
Answers
Suggested answer: C

Which statement about velocity is CORRECT?

A.
It is based on the concept of rationalism
A.
It is based on the concept of rationalism
Answers
B.
It is shown by the ideal line on a bum-down chart
B.
It is shown by the ideal line on a bum-down chart
Answers
C.
It describes how much work is getting done
C.
It describes how much work is getting done
Answers
D.
It tracks the time and cost of a timebox
D.
It tracks the time and cost of a timebox
Answers
Suggested answer: C

Explanation:

Reference: https://worldofagile.com/blog/velocity/

Which is a purpose of the ‘controlling stage’ process?

A.
To execute and deliver the project product
A.
To execute and deliver the project product
Answers
B.
To establish whether the project is complete
B.
To establish whether the project is complete
Answers
C.
To report stage progress to the project board
C.
To report stage progress to the project board
Answers
D.
To draft the plan for the next stage’s work
D.
To draft the plan for the next stage’s work
Answers
Suggested answer: C

Explanation:

Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_117&showNav=true&expandNav=true#:~:text=The%20purpose%20of%20the%20Controlling,the%20stage%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control

Which is a typical characteristic of ‘business as usual’ work?

A.
It requires a specific dedicated project manager
A.
It requires a specific dedicated project manager
Answers
B.
It is executed by program management
B.
It is executed by program management
Answers
C.
It is delivered by a temporary team
C.
It is delivered by a temporary team
Answers
D.
It is delivered by an established team
D.
It is delivered by an established team
Answers
Suggested answer: D

Explanation:

Reference: https://www.prince2primer.com/prince2-agile-overview-part-1/