What should be emphasized when tailoring the PRINCE2 Progress theme?

A.
Monitoring what is being delivered
A.
Monitoring what is being delivered
Answers
B.
Tracking time and cost
B.
Tracking time and cost
Answers
C.
Planning resources
C.
Planning resources
Answers
D.
Assessing the impact of risks
D.
Assessing the impact of risks
Answers
Suggested answer: A

When should PRINCE2 Agile be used?

A.
When a team is created to deliver a specific product
A.
When a team is created to deliver a specific product
Answers
B.
When delivering an ongoing service to a customer
B.
When delivering an ongoing service to a customer
Answers
C.
When an established team performs product maintenance
C.
When an established team performs product maintenance
Answers
D.
When simple requests to update a product are implemented
D.
When simple requests to update a product are implemented
Answers
Suggested answer: C

Which statement about the ‘protect the level of quality’ target is CORRECT?

A.
It is achieved by ensuring that all features are delivered
A.
It is achieved by ensuring that all features are delivered
Answers
B.
It is unlikely to be achieved if incomplete user documentation is provided
B.
It is unlikely to be achieved if incomplete user documentation is provided
Answers
C.
It allows change at the detailed level to be handled dynamically
C.
It allows change at the detailed level to be handled dynamically
Answers
D.
It avoids the use of extra people to improve progress during a timebox
D.
It avoids the use of extra people to improve progress during a timebox
Answers
Suggested answer: A

What is the MOST LIKELY benefit from frequent releases into operational use?

A.
Feedback is obtained from real customers
A.
Feedback is obtained from real customers
Answers
B.
The need for customer involvement is increased
B.
The need for customer involvement is increased
Answers
C.
The risks associated with agile ways of working are assessed
C.
The risks associated with agile ways of working are assessed
Answers
D.
The need for configuration management is reduced
D.
The need for configuration management is reduced
Answers
Suggested answer: A

Which is an advantage of frequent releases?

A.
Releases can be used to replace management stages
A.
Releases can be used to replace management stages
Answers
B.
A ‘one-team’ culture in the project team is encouraged
B.
A ‘one-team’ culture in the project team is encouraged
Answers
C.
Configuration management becomes less important
C.
Configuration management becomes less important
Answers
D.
The delivery team becomes more experienced at product handover
D.
The delivery team becomes more experienced at product handover
Answers
Suggested answer: D

Which TWO statements describe a purpose of the business case?

1) To define the acceptance criteria for what the project must deliver.

2) To transfer responsibility for the work to the appropriate delivery team.

3) To document how significant risks will affect the expected project benefits.

4) To outline how and when the anticipated benefits can be measured.

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: C

Which is a purpose of the ‘managing product delivery’ process?

A.
To plan the delivery of the products before committing to significant expenditure
A.
To plan the delivery of the products before committing to significant expenditure
Answers
B.
To agree on what is required for accepting, executing and delivering project work.
B.
To agree on what is required for accepting, executing and delivering project work.
Answers
C.
To establish and deliver the project communications to the wider organization
C.
To establish and deliver the project communications to the wider organization
Answers
D.
To delegate day-to-day management of the project to the project manager
D.
To delegate day-to-day management of the project to the project manager
Answers
Suggested answer: B

How does PRINCE2 Agile describe Scrum?

A.
Scrum is an IT method
A.
Scrum is an IT method
Answers
B.
Scrum is agile and agile is Scrum
B.
Scrum is agile and agile is Scrum
Answers
C.
Scrum is the most well-known agile framework
C.
Scrum is the most well-known agile framework
Answers
D.
Scrum is a project management framework
D.
Scrum is a project management framework
Answers
Suggested answer: C

Which statement about the ‘directing a project’ process is CORRECT?

A.
The project board may pull reports from the information radiator
A.
The project board may pull reports from the information radiator
Answers
B.
As a minimum, the project board should receive oral reports from the project manager
B.
As a minimum, the project board should receive oral reports from the project manager
Answers
C.
The project board should attend the delivery team’s daily stand up meeting
C.
The project board should attend the delivery team’s daily stand up meeting
Answers
D.
The project board should receive regular reports focusing on cost and time overruns
D.
The project board should receive regular reports focusing on cost and time overruns
Answers
Suggested answer: A

Which statement about the PRINCE2 Agile behaviour ‘collaboration’ is CORRECT?

A.
It allows many small learnings to accumulate over time
A.
It allows many small learnings to accumulate over time
Answers
B.
It allows the delivery team to decide how best to get the job done
B.
It allows the delivery team to decide how best to get the job done
Answers
C.
It creates a shared ownership of goals
C.
It creates a shared ownership of goals
Answers
D.
It uses the most effective channel to communicate
D.
It uses the most effective channel to communicate
Answers
Suggested answer: C