Question 153 - MB-240 discussion
DRAG DROP
You have the following requirements from the scheduling team:
* Scheduling assistant results should display in neat 30-minute time slots that dictate the start time of subsequent bookings.
* Functionality should display tor all 30 resources within the company. ' Time slots should align to the top of the hour and half past the hour.
lo meet these requirements, you need to implement Intervals within Universal Resource Scheduling.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.