Litware, Inc. designers sometimes have to schedule an experienced technician and trainee to go out to a customer's home to take measurements.

One of their customers, wants a kitchen and bathroom remodel completed during the same timeframe. The customer has asked for Litware, Inc. to have both measurements completed at the same time.

Currently, Litware, Inc. does not any technicians with both kitchen remodeling and bath remodel skills. Litware, Inc. wants to use the new Quick Book functionality to schedule multiple resources to this work order.

Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 9
Correct answer: Question 9

Explanation:

Create a new requirement group template...

Add the requirement group to Multiple Room...

Create a work orde tiwth Multiple Room...

Select a time slot, and then Book...

Filter the Quick Book pop-up window..