Question 173 - MB-240 discussion
You are scheduling a customer for preventative maintenance performed on a predictable schedule.
The customer wants the work performed within two (2) days of the 15th of each month, and an Agreement has already been created.
Which three elements of the booking setup are valid? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A.
Auto Generate Work Order = Yes
B.
Preferred Resource contains data
C.
Pre-Booking Flexibility = 2 and Post Booking Flexibility = 2
D.
Preferred Resource either contains data or is blank
E.
Auto Generate Work Order = No