Question 154 - 300-615 discussion
A Cisco uCs C-Series Server powers off due to a power outage. The server should turn on when the power is restored with a fixed delay of 3 minutes. However, it remained powered off for more than 3 minutes after the engineer powered it back online. Which two actions resolve the issue (Choose two.)
A.
Configure the power-restore-policy.
B.
Configure the power restore last-state policy.
C.
Set the delay value to 180.
D.
Set the delay fixed value to 3.
E.
Configure power sync policy.