Question 52 - MB-280 discussion

Report
Export

You use business process flows for all Dynamics 365 opportunities.

Some opportunities are closed before business process flow durations are calculated.

You need to ensure that business process flow duration values are calculated.

Solution: Create a flow to update the Status Reason of the business process flow table record to 'Finished' and the Status to 'Inactive' when the opportunity is won.

Does the solution meet the goal?

A.

Yes

Answers
A.

Yes

B.

No

Answers
B.

No

Suggested answer: A

Explanation:

Creating a flow to update the Status Reason of the business process flow table record to 'Finished' and the Status to 'Inactive' upon opportunity closure ensures that the business process flow is marked as complete. This triggers the calculation of duration values.

This solution explicitly handles the process completion state, which guarantees that the business process flow duration is recorded even if the opportunity is won prematurely.