How does a performance-based maintenance plan calculate the interval between start date and planned date?
A.
Cycle length divided by (monthly performance x 12)
B.
Cycle length divided by annual performance
C.
Cycle length divided by ((scheduling period) x (cycle modification factor))
D.
Cycle length divided by (annual performance/365)